Forms for Walls 273

FIGURE 9-42

Fillers for corners.

(Source: Symons

Corporation)

ww.EasyEngineering.n

Both gang form bolts and wedge bolts are used to connect panels

and gang form ties. Gang bolts connect panel siderails and secure the

longer ends of gang form ties. The longer end on a gang form tie

allows the tie to break back and permits stripping of the gang without

disassembly. Like wedge bolts, gang form bolts make separating

adjoining gang sections easy.

Figure 9-43 shows a gang form assembly. Panels may be stacked,

one above another, to form tall walls. Stacked panels mate tightly to

minimize form joints. Lift brackets are used as attachment points for

rigging and safe handling of large gangs. For some applications,

walers and strongbacks are used only for alignment. However, some

applications use high-capacity ties with walers and strongbacks to

gather the load of the panels. Therefore, the load is actually placed on

the ties through the walers and strongbacks. Because of the strength

and rigidity of the system, ties may be placed farther apart than they

would normally be in conventional gang forming. Recommendations

of manufacturers should be followed for safe assembly and application

of modular panels for gang forms.