IBI GROUP<br />

SHORT RANGE TRANSIT PLAN REPORT<br />

OMNITRANS COMPREHENSIVE OPERATIONAL ASSESSMENT<br />

& SHORT RANGE TRANSIT PLAN<br />

A schedule of liquidated damages and incentives has been established for each OmniLink service based<br />

on a combination of hourly productivity and on-time performance. Monthly penalties are assigned if<br />

productivity goes below 3.50 and 2.30 passengers per revenue hour for the Yucaipa and Chino Hills<br />

services, respectively. Monthly incentives are assigned if the productivity standards are exceeded<br />

without falling below the on-time performance standard.<br />

On-Time Performance<br />

One hundred percent on-time performance has been established as a goal for both Chino Hills and<br />

Yucaipa OmniLink services. A minimum standard of 95% has been established for both services. A<br />

schedule of monthly penalties has been established if on-time performance falls below the minimum. The<br />

schedule of incentives is tied to performance above the minimum and is contingent on meeting the<br />

productivity minimums.<br />

A series of monthly penalties is assessed for each trip picked up or no-showed 60 minutes or later than<br />

the service window. This penalty increases incrementally as the time delay per trip increases.<br />

Operating Costs and Productivity<br />

Chino Hills OmniLink annual operating costs have increased by over 70% for the period FY 2002/03 to<br />

FY 2005/06. This has been driven by a 50% and 95% increase in annual revenue hours and revenue<br />

miles, respectively, as well as an almost 9% increase in the cost per revenue hour. Chino Hills OmniLink<br />

operating costs per passenger increased by almost 11% and the subsidy cost per passenger increased<br />

by almost 12%.<br />

Yucaipa OmniLink annual operating costs have increased by almost 20% for the period FY 2001/02 to FY<br />

2005/06, while annual revenue hours and revenue miles decreased by 13% and 10%, respectively.<br />

While not service volume-driven, annual operating cost increases were impacted by a 44% increase in<br />

the operating cost per revenue hour. Yucaipa OmniLink operating costs per passenger increased by 32%<br />

and the subsidy cost per passenger increased by 44%. Annual ridership also decreased by<br />

approximately 9% during this period.<br />

Service productivity (passengers carried per revenue hour) decreased for Chino Hills OmniLink by almost<br />

2% from 2.24 passengers per revenue hour in FY 2002/03 to 2.20 in FY 2005/06. However, significant<br />

productivity gains (48%) were made between FY 2003/04 (when service productivity hit a period low of<br />

1.49 passengers per revenue hour) and FY 2005/06.<br />

Yucaipa OmniLink hourly service productivity increased by over 9% for the period, from 2.91 passengers<br />

per revenue hour in FY 2001/02 to 3.18 in FY 2005/06.<br />

While service productivity gains have been made, both the Chino Hills and Yucaipa OmniLink services<br />

have not been able to reach the current service standard minimums established for each service (2.30<br />

passengers per revenue hour for Chino Hills OmniLink and 3.50 for Yucaipa OmniLink). To reach the<br />

respective productivity standards, fewer annual service hours should have been operated. Given the<br />

annual ridership for each service in FY 2005/06:<br />

Farebox Recovery<br />

• Chino Hills OmniLink would have had to operate approximately 5,652 annual<br />

revenue hours.<br />

• Yucaipa OmniLink would have had to operate approximately 12,578 hours.<br />

Farebox recovery ratios have dropped for both OmniLink services over the evaluation timeframe.<br />

Ridership has increased by over 62% on the Chino Hills OmniLink service (between FY 2002/03 and FY<br />

July 11, 2007 45