New Runway Project Strategy<br />

Milestones and Phases<br />

There are 6 major milestones to be achieved in <strong>the</strong> course of this project, as follows:<br />

· Gate 1 – <strong>Business</strong> <strong>Plan</strong> Endorsement by December 2008<br />

· Gate 2 – Amended <strong>Master</strong> <strong>Plan</strong> Endorsement by December 2010<br />

· Gate 3 – Approvals to Proceed by July 2012<br />

· Gate 4 – <strong>Business</strong> Strategy Endorsement by August 2014<br />

· Gate 5 – Funding Secured by August 2016<br />

· Gate 6 – New Runway and Terminal Commissioned by February 2020<br />

To achieve <strong>the</strong> milestones, a work breakdown structure has been developed, and <strong>the</strong><br />

project has been broken down into 5 phases as illustrated in <strong>the</strong> figures below.<br />

Phase 1<br />

Concept<br />

to Sep 07<br />

<strong>Master</strong> <strong>Plan</strong><br />

Development<br />

Council<br />

Approval of<br />

Concept<br />

Engagement<br />

Gate 0<br />

Concept Approval<br />

Phase 2<br />

Feasibility<br />

Sep 07 – Dec 08<br />

Jan 09 – Jun 11<br />

<strong>Business</strong><br />

<strong>Plan</strong>ning<br />

Gate 1<br />

<strong>Business</strong> <strong>Plan</strong><br />

Endorsement<br />

Conduct<br />

Feasibility<br />

Studies<br />

<strong>Master</strong> <strong>Plan</strong><br />

Review &<br />

Amendment<br />

Engagement<br />

Gate 2<br />

Amended <strong>Master</strong><br />

<strong>Plan</strong> Endorsed<br />

Phase 3<br />

Preparation<br />

Jun 11 – Jul 12<br />

Aug 12 – Aug 14<br />

Apply For<br />

Approvals<br />

Gate 3<br />

Approvals to<br />

Proceed<br />

Prepare<br />

<strong>Business</strong><br />

Strategy<br />

Engagement<br />

Gate 4<br />

<strong>Business</strong> Strategy<br />

Endorsement<br />

Phase 4<br />

Execution<br />

Sep 14 – Aug 16<br />

Sep 16 – Feb 20<br />

Implement<br />

<strong>Business</strong><br />

Strategy<br />

Gate 5<br />

Funding Secured<br />

Construction<br />

Commssioning<br />

Engagement<br />

Gate 6<br />

New Runway &<br />

Terminal Open<br />

Phase 4<br />

Review<br />

Mar 20 – Apr 20<br />

Project<br />

Completion<br />

Prepare <strong>for</strong><br />

new <strong>Master</strong><br />

<strong>Plan</strong><br />

Engagement<br />

Project Work Breakdown Structure<br />

Sunshine Coast Airport Commercial – In – Confidence 9