CONSTRUCTION PROJECT MANAGEMENT 17.35<br />

FIGURE 17.16 Record for expediting approvals of shop drawings, change orders, samples, <strong>and</strong><br />

miscellaneous items.<br />

that, in effect, sets design <strong>and</strong> construction on separate tracks parallel to each other,<br />

rather than in consecutive sequence.<br />

The advantage of fast tracking is that a considerable amount of time is saved if<br />

construction can indeed proceed simultaneously with, <strong>and</strong> in conjunction with, the<br />

design. Presumably, job completion will take place shortly after completion of the<br />

design or, certainly, much earlier than it otherwise would have.<br />

The disadvantages of fast tracking are that in coordination of the work, the<br />

necessary input from various consultants will be largely lacking or after the fact.