THE BUILDING TEAM—MANAGING THE BUILDING PROCESS 2.29<br />

completion of the work has occurred. All required operating manuals <strong>and</strong> maintenance<br />

instructions are given to the architect for document control <strong>and</strong> forwarding<br />

to the client.<br />

10. The contractor submits final waivers of lien from each subcontractor or<br />

material supplier. Also provided is an affidavit stating that all invoices have been<br />

paid, with the exception of those amounts shown on the final waiver of lien. With<br />

these documents, the contractor submits the final consolidated payment request,<br />

including all change orders.<br />

11. The architect sends a final certificate of payment to the client, with a copy<br />

to the contractor.<br />

12. The contractor provides any required certificate of occupancy, indicating that<br />

the building authorities have jurisdiction over the project approve occupancy of the<br />

space for the intended use.<br />

13. The client makes final payment to the contractor <strong>and</strong> notifies the architect<br />

of this.<br />

This process is important inasmuch as it can trigger the transfer of risk from the<br />

contractor’s insurance program during construction to the client’s insurance program<br />

for the completed project.<br />

2.24 TESTING AND BALANCING OF BUILDING<br />

SYSTEMS<br />

It is normal for projects to go through what is known as a shakedown period after<br />

final acceptance <strong>and</strong> occupancy by the client or building tenant. The warranty <strong>and</strong><br />

guarantee period (normally 1 year) is the contractor’s representation <strong>and</strong> recognition<br />

that certain building elements <strong>and</strong> systems may need adjustment or slight modification,<br />

depending on actual occupancy conditions or normal maintenance <strong>and</strong> usage<br />

of such systems. The heating, ventilating, air conditioning, <strong>and</strong> systems unique to<br />

a project require testing <strong>and</strong> balancing <strong>and</strong> potential minor modifications <strong>and</strong> adjustments<br />

during this warranty <strong>and</strong> guarantee period, even though they were tested<br />

<strong>and</strong> balanced by the contractor’s testing agency prior to project closeout. An independent<br />

testing <strong>and</strong> balancing contractor who was employed prior to final project<br />

closeout normally returns on an as-needed, on-call basis to adjust, test, <strong>and</strong> balance<br />

systems during the first year. In addition, the building engineer will become familiar<br />

with the systems during this first year of operation <strong>and</strong> may also adjust <strong>and</strong> balance<br />

systems.<br />

2.25 POSTCONSTRUCTION OPERATION AND<br />

MAINTENANCE<br />

The technical specifications for a building project normally require that some time<br />

be devoted prior to project closeout for instruction <strong>and</strong> training of the client’s building<br />

operating personnel <strong>and</strong> building engineer, who will be responsible for operating<br />

<strong>and</strong> maintaining the various building systems. Manufacturers’ operating procedures,<br />

manuals, <strong>and</strong> inventory of spare parts <strong>and</strong> attic stock should be reviewed with the