28.02.2013 Views

Building Design and Construction Handbook - Merritt - Ventech!

Building Design and Construction Handbook - Merritt - Ventech!

Building Design and Construction Handbook - Merritt - Ventech!

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

7.120 SECTION SEVEN<br />

There is an established sequence for completing the connections. The raising<br />

gang connects members together with temporary fitting-up bolts. The number of<br />

bolts is kept to a minimum, just enough to draw the joint up tight <strong>and</strong> take care of<br />

the stresses caused by deadweight, wind, <strong>and</strong> erection forces. Permanent connections<br />

are made as soon as alignment is within tolerance limits. Usually, permanent<br />

bolting or welding follows on the heels of the raising gang. Sometimes, the latter<br />

moves faster than the gang making the permanent connections, in which case it<br />

may be prudent to skip every other floor, thus obtaining permanent connections as<br />

close as possible to the derrick—a matter of safe practice.<br />

Some erectors prefer to use permanent high-strength (A325 <strong>and</strong> A490) bolts for<br />

temporary fitting up. Because bolts used for fit-up are not tightened to specified<br />

minimum tension, they may be left in place <strong>and</strong> later tightened as required for<br />

permanent installation.<br />

7.41 FIELD-WELDING PROCEDURES<br />

The main function of a welding sequence is to control distortion due primarily to<br />

the effects of welding heat. In general, a large input of heat in a short time tends<br />

to produce the greatest distortion. Therefore, it is always advisable, for large joints,<br />

to weld in stages, with sufficient time between each stage to assure complete dispersal<br />

of heat, except for heat needed to satisfy interpass-temperature requirements<br />

(Art. 7.3.5). Equally important, <strong>and</strong> perhaps more efficient from the erector’s viewpoint,<br />

are those methods that balance the heat input in such a manner that the<br />

distortional effects tend to cancel out.<br />

Welding on one flange of a column tends to leave the column curled toward the<br />

welded side cooling, because of shrinkage stresses. A better practice for beams<br />

connecting to both sides of a column is to weld the opposite connections simultaneously.<br />

Thus the shrinkage of each flange is kept in balance <strong>and</strong> the column remain<br />

plumb.<br />

If simultaneous welding is not feasible, then the procedure is to weld in stages.<br />

About 60% of the required weld might be applied on the first beam, then the joint<br />

on the opposite flange might be completely welded, <strong>and</strong> finally, welded on the first<br />

beam would be completed. Procedures such as this will go far to reduce distortion.<br />

FIGURE 7.61 Indication of sequence in welding<br />

a connection.<br />

Experience has shown that it is good<br />

practice to commence welding at or near<br />

the center of a building <strong>and</strong> work outward.<br />

Columns should be checked frequently<br />

for vertical alignment, because<br />

shrinkage in the welds tends to shorten<br />

the distance between columns. Even<br />

though the dimensional change at each<br />

joint may be very small, it can accumulate<br />

to an objectionable amount in a<br />

long row of columns. One way to reduce<br />

the distortion is to allow for<br />

shrinkage at each joint, say, 1 ⁄16 in for a<br />

20-ft bay, by tilting or spreading the col-<br />

umns. Thus, a spread of 1 ⁄8 in for the two ends of a beam with flanges butt welded<br />

to the columns may be built in at the fabricating shop; for example, by

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!