28.02.2013 Views

Building Design and Construction Handbook - Merritt - Ventech!

Building Design and Construction Handbook - Merritt - Ventech!

Building Design and Construction Handbook - Merritt - Ventech!

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

STRUCTURAL STEEL CONSTRUCTION 7.123<br />

izontal slotted (Art. 7.3.1), thus providing some built-in adjustment to accommodate<br />

mill <strong>and</strong> shop tolerances for beams <strong>and</strong> columns.<br />

Similarly, for beams with framed connections (Fig. 7.46 <strong>and</strong> 7.47) that will be<br />

field bolted to columns, allowance should be made in the details for finger-type<br />

shims, to be used where needed for column alignment.<br />

Because of several variables, bearing of column joints is seldom in perfect contact<br />

across the entire cross-sectional area. The AISC recommends acceptance if<br />

gaps between the bearing surfaces do not exceed 1 ⁄16 in. Should a gap exceed 1 ⁄16<br />

in <strong>and</strong> an engineering investigation shows need for more contact area, the gap may<br />

be filled with mild steel shims.<br />

Tolerance for placing machinery directly on top of several beams is another<br />

problem occasionally encountered in the field. The elevation of beam flanges will<br />

vary because of permissible variations for mill rolling, fabrication, <strong>and</strong> erection.<br />

This should be anticipated <strong>and</strong> adequate shims provided for field adjustments.<br />

7.43 ADJUSTING LINTELS<br />

Lintels supported on the steel frame (sometimes called shelf angles) may be permanently<br />

fastened in the shop to the supporting sp<strong>and</strong>rel beam, or they may be<br />

attached so as to allow adjustment in the field (see Fig. 7.9, p. 7.21). In the former<br />

case, the final position is solely dependent on the alignment obtained for the sp<strong>and</strong>rel<br />

itself, whereas for the latter, lintels may be adjusted to line <strong>and</strong> grade independently<br />

of the sp<strong>and</strong>rel. Field adjustment is the general rule for all multistory<br />

structures. Horizontal alignment is obtained by using slotted holes in the connection<br />

clip angles. Vertical elevation (grade) is obtained with shims.<br />

When walls are of masonry construction, a reasonable amount of variation in<br />

the position of lintels may be absorbed without much effort by masons. So the<br />

erector can adjust the lintels immediately following the permanent fastening of the<br />

sp<strong>and</strong>rels to the columns. This procedure is ideal for the steel erector, because it<br />

allows him to complete his contract without costly delays <strong>and</strong> without interference<br />

with other trades. Subsequent minor variations in the position of the lintels, because<br />

of deflection or torsional rotation of the sp<strong>and</strong>rel when subjected to deadweight of<br />

the floor slab, are usually absorbed without necessitating further lintel adjustment.<br />

With lightweight curtain walls, however, the position of the lintels is important,<br />

because large paneled areas afford less latitude for variation. As a rule, the steel<br />

erector is unable to adjust the lintels to the desired accuracy at the time the main<br />

framework is erected. If the erector has contracted to do the adjusting, this work<br />

must wait until the construction engineer establishes the correct lines <strong>and</strong> grades.<br />

In the usual case, floor slabs are concreted immediately after the steelwork is inspected<br />

<strong>and</strong> accepted. The floor grades then determined become the base to which<br />

the lintels can be adjusted. At about the same time, the wall contractor has scaffolds<br />

in place, <strong>and</strong> by keeping pace with wall construction, the steel erector, working<br />

from the wall scaffolds, adjusts the lintels.<br />

In some cases, the plans call for concrete encasement of the sp<strong>and</strong>rel beams, in<br />

which case concreting is accomplished with the floor slab. The construction engineer<br />

should ensure that the adjustment features provided for the lintels are not<br />

frozen in the concrete. One suggestion is to box around the details, thus avoiding<br />

chopping out concrete. In some cases, it may be possible to avoid the condition<br />

entirely by locating the connection below the concrete encasement, where the adjustment<br />

is always accessible.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!