CONSTRUCTION PROJECT MANAGEMENT 17.39<br />

FIGURE 17.19 Change-order proposal submitted by a contractor to an owner to request issuance<br />

of a change order.<br />

a claim on the part of the contractor. In making a claim, the contractor may request<br />

that a change order be issued prior to proceeding with the work. Or the contractor<br />

may nevertheless proceed with the work so as not to delay the job, but request that<br />

a change order be issued. Such a request is made in the form of a change-order<br />

proposal (Fig. 17.19). Depending on the size of the claim <strong>and</strong> the attitude of the<br />

owner or architect, the contractor may decide whether to continue with the extra