17.36 SECTION SEVENTEEN<br />

This may necessitate redoing certain work, or at best, repairing deficiencies that<br />

are discovered only after portions of the construction are in place.<br />

Another disadvantage of fast tracking is that much less control exists over costs<br />

than in a job where designs are complete when prices are solicited. This disadvantage<br />

can be partly overcome, however, if the work is given to reputable, carefully<br />

prequalified subcontractors <strong>and</strong> suppliers. Certain rules of thumb from past jobs<br />

certainly will give an indication of what the final cost will be. But because of the<br />

expected loss of efficiency <strong>and</strong> redoing of certain parts of the work, costs can be<br />

expected to be higher. Nevertheless, such cost increases could be offset by resultant<br />

savings in interest on construction loans, revenues accruing from earlier use of the<br />

building, <strong>and</strong> avoidance of the effects of monetary inflation on the cost of the job<br />

if it had been begun at a considerably later date.<br />

Fast tracking lends itself particularly to professional construction management<br />

as a form of contract, although the cost-plus-fixed-fee or cost-plus-percentage-fee<br />

contract is applicable as well. (See also Art. 2.18.)<br />

17.14 CHANGES, CLAIMS,<br />

AND DISPUTE RESOLUTION<br />

After a construction contract has been awarded to a contractor, <strong>and</strong> usually after<br />

construction has begun, it may become necessary to make changes in the work that<br />

are not covered by the contract documents. To avoid writing a new contract whenever<br />

a work change is made, construction contracts usually include provisions for<br />

change orders. These are legal documents that provide a means by which an owner<br />

can order changes in the work or require extra work. Change orders may be issued<br />

for the following reasons:<br />

1. Change in scope. Specifications for building construction include a ‘‘Scope<br />

of the Project,’’ which includes a general verbal description of the project. The<br />

details are given in the technical sections of the specifications, each of which provides<br />

a ‘‘Scope of the Work.’’ This is a statement of the work to be done under<br />

that section. If any change is to be made in the project, a scope becomes involved.<br />

Usually, the specifications give the owner the right to make changes in scope, with<br />

specified compensation to the contractor.<br />

2. Change in material or installed equipment. For any of a variety of reasons,<br />

such as unavailability of a specified item or cost or time savings resulting from a<br />

substitution, the owner or the contractor may request a change in building materials<br />

or installed equipment.<br />

3. Change in expected conditions. After the start of a project, a contractor may<br />

encounter conditions not anticipated by the building designers <strong>and</strong> not covered by<br />

the contract documents. For example, during excavation for the building foundations,<br />

subsurface conditions may be encountered that are different from those described<br />

in the plans <strong>and</strong> specifications. Or abnormal weather may interfere with<br />

progress of the work or may damage work already completed. Or labor strikes may<br />

occur. Change orders may be required to accommodate these unexpected conditions.<br />

4. Change to correct omissions. During construction, the owner or the contractor<br />

may discover that certain necessary work or extra work desired by the owner is not<br />

covered by the contract documents. The owner will have to issue a change order<br />

for performance of that work.