2.12 SECTION TWO<br />

2.9 ACCELERATED DESIGN AND<br />

CONSTRUCTION<br />

The traditional process of design <strong>and</strong> construction <strong>and</strong> the roles <strong>and</strong> responsibilities<br />

of the various parties need not be changed when fast track, an accelerated design<br />

<strong>and</strong> construction process, is required. However, this process can affect scheduling<br />

<strong>and</strong> personnel assignments.<br />

In the traditional process, the entire facility moves phase by phase through the<br />

entire development process, that is, programming, design, design development, construction<br />

documents, bid <strong>and</strong> award of contracts, construction <strong>and</strong> acceptance of<br />

completed project (Art. 2.7). With any form of accelerated design <strong>and</strong> construction,<br />

the final phases remain substantially the same, but the various building systems or<br />

subsystems move through the development process at different times <strong>and</strong> result in<br />

the release of multiple construction contracts at various times throughout the process.<br />

For any project, basic building siting is determined early in the design process.<br />

Therefore, at an early stage in design, a construction contract can be awarded for<br />

demolition <strong>and</strong> excavation work. Similarly, basic structural decisions can be made<br />

before all details of the building are established. This permits early award of foundation,<br />

below grade utility work, <strong>and</strong> structural work contracts. Under such circumstances,<br />

construction can be initiated early in the design process, rather than at the<br />

conclusion of a lengthy design <strong>and</strong> contract preparation period. Months <strong>and</strong> even<br />

years can be taken out of the traditional project schedule, depending on the scale<br />

<strong>and</strong> complexity of the project. Purchase of preengineered, commercially available<br />

building systems can be integrated into the accelerated design <strong>and</strong> construction<br />

process when st<strong>and</strong>ard system techniques are employed, reducing time even more.<br />

The major requirements for a project in which design <strong>and</strong> construction occur<br />

simultaneously are<br />

• Accurate cost management to maintain project budgets.<br />

• Full underst<strong>and</strong>ing of the construction process by the client, contractor, <strong>and</strong> design<br />

professionals so that design decisions <strong>and</strong> contract documents for each building<br />

system or subsystem can be completed in a professional manner that addresses<br />

the requirements of the ongoing construction process.<br />

• Organized <strong>and</strong> efficient management of the construction process with feedback<br />

into the design process to maintain a clear definition of the required contract<br />

packages <strong>and</strong> schedule.<br />

• Overall project cost control <strong>and</strong> project construction responsibilities, including<br />

interface management of independent prime contracts, should also be established.<br />

Often the major purpose of accelerated design <strong>and</strong> construction is to reduce the<br />

effect of rapidly increasing construction costs <strong>and</strong> inflation over the extended project<br />

design <strong>and</strong> construction period. For projects extending over several years, for example,<br />

contractors <strong>and</strong> subcontractors have to quote costs for providing material<br />

<strong>and</strong> labor that may be installed several years later. In most cases, the costs associated<br />

with such work are uncertain. Bid prices for such work, especially when it<br />

is of large magnitude, therefore, must be conservative. Accelerated design <strong>and</strong> construction,<br />

however, brings all the financial benefits of a shortened project duration<br />

<strong>and</strong> early occupancy <strong>and</strong> reduces the impact of cost escalation. Also, bid prices can<br />

be closer to the actual costs, thus reducing bidding risk to the contractor. The