Financial Performance Report – December 2011<br />

Capital Expenditure<br />

• Planned and actual capital expenditure by month is<br />

summarised in the adjacent graph.<br />

• Amendments to the programme have been approved<br />

by SIRG to reflect the fall in expected expenditure on<br />

land purchases to £3.75m:<br />

• toxicology analysers £480k<br />

• breast services ultrasound £250k<br />

• fibroscan technology £47k<br />

• IT data storage £700k<br />

• IT review – systems enhancement £50k<br />

• cleaning robots £66k<br />

• medical equipment b/f from 12/13 £400k<br />

• boiler replacement £240k<br />

• initial estates rationalisation works £350k<br />

• December expenditure was lower than planned for the<br />

month at £0.5m primarily related to statutory standards<br />

and paediatric ward refurbishment.<br />

5,000<br />

4,500<br />

4,000<br />

3,500<br />

3,000<br />

2,500<br />

2,000<br />

1,500<br />

1,000<br />

500<br />

0<br />

Planned and Actual Capital Expenditure £000<br />

Actual Expenditure<br />

Planned Expenditure<br />

Paybill & Workforce<br />

• Workforce numbers, including the impact of agency workers, are approximately 160 below plan for December<br />

compared with 80 below plan in November. Excluding the impact of agency staff, wte numbers are around 239 below<br />

plan. Actual wtes have fallen by approximately 31 compared with November.<br />

• Total pay costs (including agency workers) are £698,000 lower than budgeted levels for the month , particularly on<br />

medical, scientific & therapeutic and support staff groups.<br />

• Expenditure for agency staff in December was £361,000 compared with £315,000 in November, an average of<br />

£540,000 for the year to date and a December 2010 spend of £563,000. The biggest single group accounting for agency<br />

expenditure remains medical staffing.<br />

Budgeted and Actual WTEs (Including Agency Workers)<br />

Budgeted and Actual Paybill £000<br />

7,500<br />

7,000<br />

6,500<br />

6,000<br />

5,500<br />

5,000<br />

26,000<br />

24,000<br />

22,000<br />

20,000<br />

18,000<br />

16,000<br />

14,000<br />

12,000<br />

10,000<br />

Actual WTEs<br />

Budgeted WTEs<br />

Agency Actual excl Agency Budgeted Paybill<br />