SWBTB (1/12) 274<br />
TRUST BOARD<br />
DOCUMENT TITLE:<br />
The NHS Performance Framework Monitoring Report and<br />
summary performance assessed against the NHS FT<br />
Governance Risk Rating (FT Compliance Report)<br />
SPONSORING DIRECTOR:<br />
AUTHOR:<br />
DATE OF MEETING: 26 <strong>January</strong> <strong>2012</strong><br />
Robert White, Director of Finance and Performance Mgt<br />
Mike Harding, Head of Planning & Performance Management<br />
and Tony Wharram, Deputy Director of Finance<br />
SUMMARY OF KEY POINTS:<br />
The report provides an assessment of the Trust’s performance mapped against the indicators which<br />
comprise the NHS Performance Framework.<br />
Service Performance (December and Quarter 3):<br />
There are 2 areas of underperformance during the month of December. These are A/E 4-hour waits and<br />
Delayed Transfers of Care. Actual performance is as indicated in the attached report. The overall score<br />
for the month is 2.57. There is 1 area of underperformance during Quarter 3, Delayed Transfers of Care.<br />
The overall score for the Quarter is 2.93.<br />
A score in excess of 2.40 attracts a PERFORMING classification.<br />
Financial Performance (December):<br />
The weighted overall score remains 2.90 and is classified as PERFORMING. Underperformance is<br />
indicated in December in 3 areas; Better Payment Practice Code (Value), Better Payment Practice<br />
Code (Volume) and Creditor Days.<br />
Foundation Trust Compliance Summary report:<br />
There was 1 area of underperformance reported within the framework during the month of December.<br />
A/E 4-hour waits performance was 94.0%. As such the overall score for the month is 1.0, which attracts an<br />
AMBER / GREEN Governance Rating.<br />
There were no areas of underperformance reported within the framework for the Quarter 3 period. As<br />
such the overall score for the Quarter is 0.0, which attracts a GREEN Governance Rating.<br />
PURPOSE OF THE REPORT (Indicate with ‘x’ the purpose that applies):<br />
Approval Receipt and Noting Discussion<br />
x<br />
ACTIONS REQUIRED, INCLUDING RECOMMENDATION:<br />
The Trust Board is asked to NOTE the report and its associated commentary.<br />