Territorial context of the project<br />

Visual impact of the project<br />

In this section, the Panel considers the visual impact of the LNG terminal. As regards<br />

the natural gas pipeline, the only modifications to the landscape to be noted are the<br />

visual impact of a corridor through a forest environment and possible temporary<br />

trenches for the river crossings. Revegetation work is planned once the trenches are<br />

refilled. Local adjustments could also be made by the proponent to ensure good visual<br />

integration of the natural gas pipeline (PR3.4.1, p. 6-11).<br />

The area of visibility of the LNG terminal project considered by the proponent for his<br />

analyses is illustrated in Figure 6. According to certain participants, the area of<br />

visibility reaches farther and the analysis should have included Québec City and other<br />

municipalities on the south shore and île d’Orléans.<br />

The permanent infrastructures, operational activities, and nighttime lighting would be<br />

the main sources of visual impact for the project. The most visible infrastructures<br />

would be the following:<br />

– The service corridor including the access road to the jetty and the right-of-way for<br />

the cryogenic pipes, part of which would be cut into the cliff.<br />

– The 500-m long jetty.<br />

– The 20-m high water towers and the 19-m high unloading arms located at the jetty<br />

head.<br />

– The buildings on the shoreline.<br />

– The storage tanks, visibly 46-m high and 90-m in diameter.<br />

– The vaporizer stacks.<br />

– The 60-m high flare.<br />

– The two 230-kV electricity supply lines involving a 60-m right-of-way requiring<br />

control of wooded vegetation.<br />

– The docked LNG tankers 1 .<br />

1. An LNG tanker is 300-m long, 40 to 50-m wide, and 41 to 52-m high. That corresponds to a 15 to 18-storey<br />

tower or the height of the cliff across from the zone retained for the shore and port facilities.<br />

108 Rabaska Project – Implementation of an LNG Terminal and Related Infrastructure