Assessing the risks related to the project<br />

The security measures planned for the pipeline<br />

The safety measures planned for this project would be taken into account for the design,<br />

construction and operation of the pipeline with the aim to prevent, detect and control any<br />

event which could occur in relation to the pipeline and to mitigate its consequences, if<br />

required. These measures would be based on risk analysis, and would especially take<br />

into consideration the most likely cause of accidents, i.e. the accidental breakage of the<br />

line caused by excavation work. Some of these measures are:<br />

– The line would be placed in a 23-m right-of-way that would meet the NEB’s<br />

standards to border or cross the electric right-of-way.<br />

– All work performed less than 30 m from the right-of-way would have to be<br />

declared.<br />

– Block valves would be placed at both ends, as well as in the middle of the<br />

pipeline, for emergency shutdowns.<br />

– Additional security measures would be implemented in the site’s slump areas.<br />

To that effect, the ministère de la Sécurité publique specified that it would continue its<br />

review to assess the need for additional pipeline security measures. However, in its<br />

opinion, barring exceptional circumstances, the guarantees provided by the proponent<br />

were satisfactory, said guarantees specifying compliance with Canadian standards,<br />

participation in the Comité mixte municipal-industries (CMMI), and the possible<br />

compliance of the emergency measures plan with the MDDEP’s guidelines. Moreover,<br />

the MDDEP specified that the CSA-Z662-03 1 standard does not make any provision<br />

for exclusion zones:<br />

[… ] depending on the proximity of some buildings, the use of various classes of<br />

pipes, or the deeper burial of the pipeline in the ground. This has an effect of<br />

decreasing the probability or frequency of occurrence of a major accident, without<br />

necessarily changing the consequences of such an accident. Implementing a 23m<br />

right-of-way for a pipeline also aims to decrease the probability that a major<br />

accident will occur, by protecting it from an accidental rupture. In spite of the<br />

measures which could decrease the frequency of accidents, keeping residences<br />

away from the pipeline route remains an essential criterion to consider when<br />

selecting the pipeline route.<br />

(DQ61.1, p. 2)<br />

The ministry is slated to examine the situation of the closest buildings in order to<br />

assess the opportunity of planning special mitigation measures for them.<br />

1. Canadian Standards Association (2005). Z662-03, Oil and Gas Systems, 439 p.<br />

154 Rabaska Project – Implementation of an LNG Terminal and Related Infrastructure