10.07.2015 Views

Architecture and management of a geological repository - Andra

Architecture and management of a geological repository - Andra

Architecture and management of a geological repository - Andra

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

7 – The shafts <strong>and</strong> the drifts7.5.1.1 The shaft construction methodsFor the construction <strong>of</strong> large diameter shafts, the conventional method consists <strong>of</strong> sinking the shaftsfrom the surface by blasting the rock with explosives or drilling the rock with a roadheader <strong>and</strong>installing as the sinking operation progresses the ground support <strong>and</strong> the liner <strong>of</strong> the shaft. Thismethod is well adapted to the planned usable diameters between 6.50 m <strong>and</strong> 11.50 m.Fully mechanised sinking methods have been developed in the mining industry. The “shaft drilling″method consists <strong>of</strong> drilling shafts with a kind <strong>of</strong> vertical tunnel drilling machine equipped with cuttingwheels. In the “raise boring” method, a ″pilot hole″ approximately 30 cm in diameter is drilled fromthe surface down to a pre-existing drift. From the drift, a boring tool is raised in the drilled section upto the surface. These technologies <strong>of</strong>fer the advantage <strong>of</strong> not requiring personnel in the shafts duringthe sinking operations, but the disadvantage <strong>of</strong> not allowing the ground support <strong>and</strong> liner <strong>of</strong> the shaftto be progressively installed during the sinking operations. Moreover, in the current state <strong>of</strong>technology, these methods are not applicable to the diameters considered.7.5.1.2 The main phases in the construction <strong>of</strong> a shaft by a conventional methodIn order to construct a shaft, a foreshaft is sunk a few tens <strong>of</strong> metres into the ground <strong>and</strong> then the shaftsinking equipment is installed. Then the main sinking operations take place. After the sinkingoperations are completed, the shaft equipment is installed <strong>and</strong> then the final machinery.• ForeshaftForeshaft construction details can vary according to the exact location <strong>of</strong> the shafts <strong>and</strong> thecharacteristics <strong>of</strong> the ground close to the surface. According to the consistency <strong>of</strong> the surface ground,the first few metres can be excavated with a dredger. The foreshaft is sunk a few tens <strong>of</strong> metres bysuccessive sinking phases with drilling <strong>and</strong> blasting <strong>and</strong> ground support by rockbolts <strong>and</strong> grillage (<strong>and</strong>shotcrete, if necessary). As soon as there is no longer any risk <strong>of</strong> damaging it with blasting, areinforced concrete slab is poured to serve as a base for the construction <strong>of</strong> the shaft.• Shaft sinking equipmentThe shaft sinking equipment is generally made up <strong>of</strong> two sub-assemblies : on the one h<strong>and</strong>, themovable equipment circulating in the shaft <strong>and</strong>, on the other h<strong>and</strong>, the fixed equipment located on thesurface.The movable equipment consists <strong>of</strong> a movable planking <strong>and</strong> a platform from which the work in theshaft is performed. The planking <strong>and</strong> platform are suspended on cables <strong>and</strong> are progressively loweredas the worksites progress.DOSSIER 2005 ARGILE -ARCHITECTURE AND MANAGEMENT OF A GEOLOGICAL DISPOSAL SYSTEM305/495

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!