10.07.2015 Views

Architecture and management of a geological repository - Andra

Architecture and management of a geological repository - Andra

Architecture and management of a geological repository - Andra

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

9 – Nuclear operating resources in the <strong>repository</strong>9.3.2.4 Description <strong>of</strong> the process <strong>of</strong> installation in the cellThe disposal cycle <strong>of</strong> B packages (illustrated by the diagram in Figure 9.3.5) takes place in four stages.Figure 9.3.5Diagram <strong>of</strong> the installation <strong>of</strong> B packages in the cellAs a first stage, the transfer cask is docked by the shuttle at the docking gate <strong>of</strong> the cell chamber. Thedisposal truck can then extract the disposal package.As a second stage, after closure <strong>of</strong> the docking door, the moveable floor rotates the disposal truckthrough 180° <strong>and</strong> moves it to face the selected disposal row.As a third stage, the sliding doors are opened <strong>and</strong> the disposal truck then enters the cell. During thetravel in the disposal chamber, the package is in the low position to prevent any risk <strong>of</strong> falling <strong>and</strong> tomake the moving truck <strong>and</strong> package stable. When it arrives next to the front <strong>of</strong> the packages alreadydisposed, the disposal truck gradually slows so that the operations <strong>of</strong> placing the package can begin.The package is lifted to the height at which it is to be deposited which can be as high as 4.50 m. Thedisposal truck advances very slowly <strong>and</strong> positions the package just above the disposal level constitutedby the package below. The package is then deposited very slowly. The operations <strong>of</strong> installing thepackages is illustrated by Figure 9.3.6 <strong>and</strong>Figure 9.3.7. Finally as a last stage, the disposal truck reverses <strong>and</strong> returns to the airlock whose slidingdoors are shut again.The time taken to complete a whole cycle <strong>of</strong> installing a package over a distance <strong>of</strong> about 120 metresis estimated to be about 2 hours from the extraction <strong>of</strong> the package from the transfer cask to the return<strong>of</strong> the empty disposal truck to the airlock.The design <strong>of</strong> equipment related to the emplacement <strong>of</strong> the packages is based on the principle <strong>of</strong> theredundancy <strong>of</strong> motorisations <strong>and</strong> their associated comm<strong>and</strong>s. In case <strong>of</strong> breakdown, the disposal truckis designed to set down its load passively. A winch system would be used to return it to the airlock.DOSSIER 2005 ARGILE -ARCHITECTURE AND MANAGEMENT OF A GEOLOGICAL DISPOSAL SYSTEM350/495

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!