PW-2.2: Exterior Water Use Reduction: Heat Rejection<br />
Intent To reduce potable water use for heat rejection by promoting the use of recycled water<br />
and/or alternatives to water-based heat rejection.<br />
Credit<br />
Requirements<br />
Awarding Credit<br />
Points<br />
Credit<br />
Submission:<br />
Design <strong>Rating</strong><br />
GENERAL<br />
Water-Based Heat Rejection<br />
Demonstrate that the following percentage of the projects cooling tower/district<br />
cooling water make-up requirements can be served using the Exterior Water Allowance<br />
(as outlined in the Calculations and Methodology section):<br />
� 2 Credit Points: > 25%<br />
� 3 Credit Points: > 50%<br />
� 4 Credit Points: > 75%<br />
� 5 Credit Points: 100%<br />
AND<br />
Where cooling towers are installed onsite and recycled water is not immediately<br />
available, demonstrate that a recycled water mainline loop has been installed which<br />
allows for the future switch from potable to recycled water in onsite cooling towers<br />
when it becomes available. All pipes containing recycled water must be color coded in<br />
order to easily distinguish them from potable water pipes.<br />
OR<br />
No Water Used for Heat Rejection<br />
� 8 Credit Points: Demonstrate that the project uses no water for heat rejection<br />
ADDITIONAL REQUIREMENT/CLARIFICATIONS<br />
None<br />
CREDIT POINTS<br />
8<br />
(maximum)<br />
2-5<br />
REQUIREMENTS<br />
Design <strong>Rating</strong><br />
Demonstrate that a percentage of the projects cooling<br />
tower/district cooling water make-up requirements can be<br />
served using the Exterior Water Allowance.<br />
8 Demonstrate that no water is required for heat rejection.<br />
8<br />
Construction <strong>Rating</strong><br />
(maximum)<br />
Demonstrate that a percentage of the projects cooling<br />
2-5 tower/district cooling water make-up requirements can be<br />
served using the Exterior Water Allowance.<br />
8 Demonstrate that no water is required for heat rejection.<br />
Water-Based Heat Rejection<br />
� <strong>Building</strong> Water Calculator confirming the percentage of the projects cooling<br />
tower/district cooling water make-up requirements that can be served using the<br />
Exterior Water Allowance; and<br />
� A composite utility schematic illustrating routing of recycled water mainline and<br />
<strong>Pearl</strong> <strong>Building</strong> <strong>Rating</strong> <strong>System</strong>: Design & Construction, Version 1.0, April 2010 129 of 223