SM-8: Material Reuse<br />
Intent To promote the selection of previously used or salvaged materials in order to reduce<br />
demand on natural resources and reduce waste<br />
Credit<br />
Requirements<br />
Awarding Credit<br />
Points<br />
Credit<br />
Submission:<br />
Design <strong>Rating</strong><br />
Credit<br />
Submission:<br />
Construction<br />
<strong>Rating</strong><br />
Calculations and<br />
Methodology<br />
GENERAL<br />
References None<br />
Demonstrate that the total material cost of reused and salvaged materials represents<br />
3% of the total material cost.<br />
The following materials are not eligible for this credit:<br />
� Materials addressed in all other credits under Stewarding Materials section<br />
except SM 9- Regional Materials;<br />
� Materials constituting the reused portion of the building's structural system as<br />
per SM-7 <strong>Building</strong> Reuse compliance criteria; and<br />
� <strong>Building</strong> components whose performance can influence the energy or water use<br />
are only eligible if an equivalent level of performance can be demonstrated in<br />
comparison to new components available in the current market.<br />
ADDITIONAL REQUIREMENT/CLARIFICATIONS<br />
None<br />
CREDIT POINTS REQUIREMENTS<br />
1<br />
(maximum)<br />
1<br />
1<br />
(maximum)<br />
1<br />
Design <strong>Rating</strong><br />
The cost of specified reused materials equal to at least 3% of the<br />
Total Material Cost.<br />
Construction <strong>Rating</strong><br />
The cost of installed reused materials equal to 3% of the Total<br />
Material Cost.<br />
� Summary sheet listing all proposed reused materials meeting the Credit<br />
Requirements, their cost, the source or location of previous use, and intended new<br />
use;<br />
� Calculations demonstrating that the total cost of the proposed reused materials<br />
meet the Credit Requirements; and<br />
� Extracts from specifications requiring the use of the proposed materials.<br />
� Updated summary sheet listing all proposed reused materials meeting the Credit<br />
Requirements, their cost, the source or location of previous use, and new use; and<br />
� Updated calculations demonstrating that the total cost of the proposed reused<br />
materials meet the Credit Requirements.<br />
Total Material Cost: exclude labor and equipment costs and include the following<br />
divisions from the Construction Specifications Institute (CSI) MasterFormat TM or<br />
equivalent: Division 03 Concrete, Division 04 Masonry, Division 05 Metals, Division 06<br />
Wood, Plastics, and Composites, Division 07 Thermal and Moisture Protection, Division<br />
08 Openings, Division 09 Finishes, Division 10 Specialties, Division 31 Earthwork,<br />
Division 32 Exterior Improvements. Division 12 may be included; however, associated<br />
costs must be carried throughout all Stewarding Materials credits.<br />
<strong>Pearl</strong> <strong>Building</strong> <strong>Rating</strong> <strong>System</strong>: Design & Construction, Version 1.0, April 2010 185 of 223