using the limited information available at the time of pit optimization. The economic<br />

and operating parameters used in the optimization are specified in Table 16.3.<br />

Table 16.3 <strong>Economic</strong> Parameters of Pit Optimization (Base Case)<br />

Items Units Value Comments<br />

Exchange Rate Cdn$:US$ 1:0.9794 -<br />

Discount Rate % 8 -<br />

Metal<br />

Prices<br />

Metal<br />

Recoveries<br />

Operating<br />

Costs<br />

Platinum US$/troy oz 2,043.50 Quarterly Update of<br />

Palladium<br />

Gold<br />

Nickel<br />

US$/troy oz<br />

US$/troy oz<br />

US$/lb<br />

932.00<br />

1,347.50<br />

10.82<br />

Long Term Metal<br />

Pricing<br />

(April 16, 2012)<br />

Copper US$/lb 3.11<br />

Cobalt US$/lb 16.70<br />

Platinum % 46.0 From Table 13.9<br />

Palladium % 72.9<br />

Gold % 58.9<br />

Nickel % 67.6<br />

Copper % 87.8<br />

Cobalt % 64.4<br />

Mining Cost US$/t mined 2.81 -<br />

Processing Cost US$/t milled 20.79 -<br />

Mining Recovery % 95 -<br />

Mining Dilution % 5 -<br />

Overall Slope Angle degrees 45 -<br />

Mill Throughput t/d 32,000 -<br />

GEOLOGICAL BLOCK MODEL<br />

t/a 11,200,000 -<br />

Tetra Tech prepared the resource geological block model using the Datamine <br />

software program. For optimization purposes, the model was reblocked using a<br />

block size of 40 m x 40 m x 20 m.<br />

Historical production records indicate that between 1972 and 1973 Hudson Yukon<br />

Mining produced 171,652 tons (155,720 t) assaying 2.23% nickel, 1.39% copper,<br />

0.065 oz/ton platinum and 0.073% cobalt. This likely does not include the drifting,<br />

which is both in and out of the mineralized material. Since the tonnage was small<br />

relative to the resource (less than 0.05% of the total resource), it was not considered<br />

to be significant to the overall resource. This will need to be addressed in advanced<br />

studies (prefeasibility and feasibility).<br />

The block model uses a local mine grid coordinate system. The pit optimization and<br />

design were <strong>com</strong>pleted using the same coordinate system.<br />

Prophecy Platinum Corp. 16-3 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada