21.2.3 CLOSURE<br />

Table 21.5 Mine Equipment Fleet Units & Costs (US$ million)<br />

Major Mine Equipment<br />

Pre-production<br />

(2012 to 2018)<br />

Sustaining<br />

(2019 to 2054)<br />

LOM Total<br />

(2012 to 2054)<br />

Units Cost Units Cost Units Cost<br />

Haul Trucks 15 66.0 57 250.6 72 316.6<br />

Shovels 3 21.4 12 85.5 15 106.9<br />

Drills 2 4.3 3 6.5 5 10.8<br />

Dozers 8 11.6 32 46.5 40 58.1<br />

Graders 3 2.8 12 11.2 15 14.0<br />

Wheel Loaders 1 5.6 3 16.7 4 22.3<br />

Labour - 0.2 - 0.0 - 0.2<br />

Contingency - 28.0 - 104.3 - 132.3<br />

Total Major Mine Equipment 32 139.9 119 521.3 151 661.2<br />

Other Mine Equipment 49 5.6 260 24.0 309 29.6<br />

Contingency - 1.4 - 6.0 - 7.4<br />

Total Other Mine Equipment 49 7.0 260 30.0 309 37.0<br />

Support Mine Equipment 16 1.1 57 4.2 73 5.3<br />

Contingency - 0.2 - 1.1 - 1.3<br />

Total Support Mine Equipment 16 1.3 57 5.3 73 6.6<br />

Total 97 148.2 436 556.6 533 704.8<br />

An estimated closure cost of US$61.2 million, including a 25% contingeny, has been<br />

applied in the last four years of the mine life, 2051 through 2054, as shown in Table<br />

21.6.<br />

Table 21.6 Closure (US$ million)<br />

Closure Capital<br />

2051 2052 2053 2054 Total<br />

Closure 15.3 15.3 15.3 15.3 61.2<br />

21.2.4 CONTINGENCY<br />

A contingency of 25% was applied to the capital cost for a total of US$409.2 million.<br />

A breakout of the <strong>Project</strong> LOM contingency for pre-production capital, sustaining<br />

capital and closure is shown in Table 21.7.<br />

Prophecy Platinum Corp. 21-4 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!