Mine Equipment<br />

21.2.2 SUSTAINING<br />

2012 2013 2014 2015 2016 2017 2018 Total<br />

Major Mine Equipment 0.0 0.0 0.0 0.0 0.0 0.0 111.9 111.9<br />

Other Mine Equipment 0.0 0.0 0.0 0.0 0.0 0.0 5.6 5.6<br />

Support Mine Equipment 0.0 0.0 0.0 0.0 0.0 0.0 1.0 1.0<br />

Contingency - - - - - - 29.7 29.7<br />

Total Mine Equipment 0.0 0.0 0.0 0.0 0.0 0.0 148.2 148.2<br />

Total Pre-production 6.2 3.3 7.1 5.5 106.9 326.8 407.3 863.1<br />

The sustaining capital period from 2019 through 2054 has a cost of<br />

US$1,121.8 million, including a 25% contingency. It is <strong>com</strong>prised of major mine<br />

equipment at US$521.3 million, other mine equipment at US$30.0 million, support<br />

mine equipment at US$5.3 million, refurbished power plant at US$61.7 million and a<br />

TMF at US$503.5 million.<br />

Sustaining capital costs are estimated to cover major repairs and replacement of<br />

mine equipment to maintain continuous mine production levels at an average rate of<br />

39 Mt moved annually for the 37-year LOM.<br />

Pricing for major mine production equipment was obtained from Tetra Tech’s inhouse<br />

cost database and CostMine’s 2010 Mine and Mill Equipment Costs Guide<br />

and has been escalated to 2012 dollars.<br />

A summary of the sustaining mine capital cost is outlined in Table 21.4.<br />

Table 21.4 Sustaining Capital (US$ million)<br />

Pre-production<br />

Sustaining Capital<br />

(2019 to 2054)<br />

Equipment Units Total Cost<br />

Major Mine Equipment 119 521.3<br />

Other Mine Equipment 260 30.0<br />

Support Mine Equipment 57 5.3<br />

Refurbished Power Plant - 61.7<br />

Tailings Management Facility - 503.5<br />

Total Sustaining 436 1,121.8<br />

A breakdown of the mine equipment fleet required for the <strong>Project</strong> is provided in Table<br />

21.5. The table itemizes fleet units and equipment costs during pre-production,<br />

sustaining and total LOM.<br />

Prophecy Platinum Corp. 21-3 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada