PHASE I<br />

Phase I consists of the pre-production year, the ramp-up period and the first year of<br />

full mill production. The initial pushback prioritizes the higher grade mineralization at<br />

the top-centre portion of the resource body, and at the lowest amount of waste<br />

stripping. This will maximize cash flow and speed the capital recovery during the<br />

initial years. Phase l will mine 67.3 Mt of rocks including 16.2 Mt of mineralized<br />

material at 0.57% NiEq. Figure 16.6 illustrates the Phase I pit at the end of Year 3.<br />

Figure 16.6 3D Rendered Image of Phase I Pit and Mineralized Area<br />

PHASE II<br />

During Phase II, the pit will deepen and expand to the west. Phase ll will involve the<br />

mining of 89.6 Mt of mineralized material, which will satisfy the capacity of the mill for<br />

8 years. Figure 16.7 illustrates the Phase II pit at the end of Year 11.<br />

Figure 16.7 3D Rendered Image of Phase II Pit and Mineralized Area<br />

Prophecy Platinum Corp. 16-15 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada