Year 39, the number of shovels required is three. In the final three years of the<br />

schedule, the shovel requirement decreases to two.<br />

The shovel size has been matched with 225 t haul trucks to provide a swing cycle of<br />

35 s and total truck load time of 4.0 min in six passes for waste material and 3.4 min<br />

in five passes for mineralized material. Suitable number of loading passes typically<br />

falls within the range of three to seven.<br />

Shovel base productivities were calculated using the sample parameters in Table 5.<br />

Table 5 Sample Shovel Productivity Calculation<br />

Prophecy Platinum Corp, 7 1193460500-REP-R0001-00<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada<br />

Units<br />

Waste<br />

Shovel<br />

Mineralized<br />

Material<br />

Shovel<br />

Bucket Capacity (Heaped) m 3 21.0 21.0<br />

Material Weight dmt/bank m 3 2.5 3.2<br />

Bulk Factor 1.3 1.3<br />

Material Weight dmt/loose m 3 1.95 2.48<br />

Moisture % 3.0 3.0<br />

Material Weight wmt/lcm 2.01 2.55<br />

Fill Factor % 95 95<br />

Effective Bucket Capacity m 3 19.95 19.95<br />

Tonnes/Pass wmt 40.0 50.9<br />

Truck Size Capacity wmt 225 225<br />

Average Number of Passes passes 6 5<br />

Truck Spot Time s 32 32<br />

First Bucket Cycle Time s 30 30<br />

Subsequent Bucket Cycle Time s 35 35<br />

Load Time Per Truck min 3.9 3.4<br />

Theoretical Maximum Productivity trucks/h 15.2 17.8<br />

dmt/h 3,315 3,890<br />

Truck Availability to Shovel % 90 90<br />

Producing Hours h/a 5,221 5,221<br />

Base Productivity wmt/net operating hour 3,073 3,605<br />

The material weights used in the sample calculation are 2.5 t/bank m 3 for waste and<br />

3.2 t/bank m 3 for mineralized material. The base productivity was used under normal<br />

ideal loading conditions. Maximum productivities for both mineralized and waste<br />

materials for the shovel and loader were reduced to 90% due to truck availability.