Table 25.4 Process Capital Cost Summary<br />

Process Area<br />

Capital<br />

Cost<br />

(US$)<br />

Mineralized Material Storage and Recovery 5,980,804<br />

Crushing 10,126,321<br />

Milling (Building and Mills) 135,723,509<br />

Flotation 19,278,854<br />

Concentrate Dewatering, Storage, and Load-out 3,314,964<br />

Reagent Preparation 2,943,091<br />

Total 177,367,543<br />

Table 25.5 Process Operating Costs<br />

US$/t milled<br />

Annual<br />

Cost<br />

(US$)<br />

Percentage<br />

(%)<br />

Electrical Power 8.14 91,157,689 47<br />

Labour 0.68 7,569,050 4<br />

Consumables 8.53 95,545,544 49<br />

Total 17.35 194,272,283 100<br />

These estimates reflect the costs entailed in producing a concentrate for sale or toll<br />

treatment only. Although further downstream pyrometallurgical or hydrometallurgical<br />

treatment of concentrates has not been assessed in the current study, additional<br />

treatment will almost certainly be evaluated in subsequent, more detailed, studies.<br />

Future work will also require testing the MF2 process flowsheet and additional<br />

downstream pyrometallurgical and hydrometallurgical concentrate treatments as<br />

described in Section 26.0 in this report. The estimated cost of the above test work is<br />

approximately US$400,000.<br />

25.4 I NFRASTRUCTURE<br />

Additional studies for the locations of the TMF and the process plant area will be<br />

required. Some geotechical and detailed topographical surveys will be required in<br />

order to <strong>com</strong>plete these studies.<br />

A trade-off study has been <strong>com</strong>missioned to <strong>com</strong>pare power generation diesel fuel<br />

versus LNG for the <strong>Project</strong>.<br />

Prophecy Platinum Corp. 25-4 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada