Table 3 Penetration and Drilling Rates<br />

Parameters Units Waste<br />

Mineralized<br />

Material<br />

Hole Depth m 12.3 12.3<br />

Penetration Rate cm/min 60.0 60.0<br />

Grade Control Sampling Time min 2.0 2.0<br />

Move, Align, Collaring Time min 3.0 3.0<br />

Total Time per Hole min 25.5 25.0<br />

Holes per Hour holes 2.4 2.4<br />

Average Drilling Rate m/h 28.9 29.5<br />

BLASTING REQUIREMENT<br />

Overall explosive consumption was based on using a 70% ammonium nitrate fuel oil<br />

(ANFO) and 30% emulsion mix product. Some blasting parameters are shown in<br />

Table 4. Drillhole liners are to be used in wet holes where practical.<br />

The selected explosive supplier is to erect a plant and storage facility on site. Under<br />

the supervision of the drill/blast foreman, the supplier will be contracted to supply,<br />

deliver, and load explosives into the blastholes. The drill/blast foreman will also<br />

oversee the blasting crew who will prime, stem, and tie-in blastholes.<br />

Table 4 Blasthole Drill Productivity and Blasting Parameters<br />

Parameters Units Waste<br />

Mineralized<br />

Material<br />

Hole Diameter cm 25.1 25.1<br />

Bench Height m 10 10<br />

Sub-grade m 2.3 2.3<br />

Powder Factor kg/t 0.27 0.21<br />

Bank Density t/m3 2.5 3.2<br />

Rock Mass Per Hole t 1,650 2,100<br />

Spacing and Burden m 8.7 x 7.5 8.7 x 7.5<br />

Drilling Rate m/h 28.9 29.5<br />

1.3.3 LOADING AND HAULING<br />

LOADING FLEET<br />

The loading fleet will consist of 21 m 3 diesel hydraulic shovels and a 18 m 3 diesel<br />

hydraulic loader as back-up. The shovel requirements include four 21 m 3 shovels for<br />

both waste and mineralized material types from Year 1 to Year 14. From Year 15 to<br />

Year 28, the shovel requirements range between three and four. From Year 29 to<br />

Prophecy Platinum Corp, 6 1193460500-REP-R0001-00<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada