Spares<br />

• safety including safety officer, training, supplies, equipment, and vehicle<br />

• quality assurance and control<br />

• temporary power supply and distribution and power costs<br />

• temporary water supply and distribution<br />

• contractors' mobilization and demobilization<br />

• temporary heating and hoarding<br />

• warehouse and lay-down costs<br />

• temporary toilets<br />

• temporary <strong>com</strong>munications (phone, fax and internet services)<br />

• ongoing and final clean-up<br />

• yard maintenance<br />

• janitorial services<br />

• site safety personnel and training<br />

• contractor’s turnaround costs<br />

• travel to and from site.<br />

Allowances of 3% are included in the indirect costs for capital and <strong>com</strong>missioning<br />

spares.<br />

Initial Fills<br />

An allowance is included in the indirect costs for initial fills.<br />

Commission and Start-up<br />

An allowance is included in the indirect costs for <strong>com</strong>missioning and start-up.<br />

Freight and Logistics<br />

An allowance is included in the indirect costs for freight and logistics.<br />

EPCM Cost<br />

Engineering, Procurement, and Construction Management (EPCM) cost is included<br />

as an allowance based a percentage of the direct cost.<br />

Prophecy Platinum Corp. 21-9 1193460500-REP-R0001-02<br />

<strong>Wellgreen</strong> <strong>Project</strong> <strong>Preliminary</strong> <strong>Economic</strong> <strong>Assessment</strong>,<br />

Yukon, Canada

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!