Chapter 4 • Specific <strong>Plan</strong> Administration<br />

improvement costs to a minimum. While retention and/or detention basins<br />

may be useful in augmenting channel construction, that option will not be<br />

defined until subsequent studies are completed.<br />

On-site drainage improvements will be funded by the project through a<br />

likely combination <strong>of</strong> developer contributions, assessments or other<br />

financing mechanisms. Peter's Canyon Channel improvements and<br />

improvements to the Santa Ana - Santa Fe Channel and Barranca Channel<br />

improvements will be satisfied as identified on Table 4-2 and in the Joint<br />

EIS/EIR.<br />

The service provider for regional flood control channels is the Orange<br />

County Flood Control District. The cities <strong>of</strong> <strong>Tustin</strong> and Irvine would be<br />

responsible for on-site drainage facilities within their respective<br />

jurisdictions with consultation with OCFCD.<br />

4.4.10 Electricity<br />

To the extent possible, backbone electrical distribution lines will be<br />

installed underground at the same time as the on-site arterial highways are<br />

constructed to serve phased development.<br />

4.4.11 Natural Gas<br />

To the maximum extent possible, the backbone natural gas distribution<br />

lines will be installed underground at the same time as the on-site arterial<br />

highways are constructed to serve phased development.<br />

4.4.12 Telephone<br />

To the maximum extent possible, backbone telephone lines will be<br />

installed underground at the same time as the on-site arterial highways are<br />

constructed to serve phased development. Fiber optic facilities are highly<br />

encouraged in conjunction with standard telephone lines.<br />

4.4.13 Cable Television<br />

To the maximum extent possible, backbone cable television lines will be<br />

installed underground at the same time as the on-site arterial highways are<br />

constructed to serve phased development.<br />

4.4.14 Parks<br />

Community and neighborhood park development by the <strong>City</strong> <strong>of</strong> <strong>Tustin</strong><br />

will be a function <strong>of</strong> when adequate park development fees or other<br />

MCAS <strong>Tustin</strong> Specific <strong>Plan</strong>/Reuse <strong>Plan</strong><br />

<strong>City</strong> <strong>of</strong> <strong>Tustin</strong><br />

Page 4-19