- Page 1 and 2: Transport and Works Act 1992Transpo
- Page 4: CONTENTSVOLUME 1INTRODUCTION, SCHEM
- Page 8: Evergreen 3 Project: The ChilternRa
- Page 12: CONTENTS1 INTRODUCTION 11.1 PURPOSE
- Page 15: capacity - which was completed in 2
- Page 19 and 20: identified for railway use in the C
- Page 22: KEY:Scheme BoundaryBicester North S
- Page 25 and 26: Currently the rail corridor is used
- Page 27 and 28: The CRCL plans for new platforms at
- Page 29 and 30: • cumulatively significant effect
- Page 31 and 32: significant effect may arise in rel
- Page 33 and 34: types arising from the project, (eg
- Page 35 and 36: • construction of new infrastruct
- Page 38 and 39: 3.3.3 In addition along the corrido
- Page 40: WarwickshireNorthamptonshireTingewi
- Page 43 and 44: Habitats3.4.8 ERM undertook a preli
- Page 45 and 46: Habitats3.4.17 The works may involv
- Page 47 and 48: Due to the limited land-take of the
- Page 50 and 51: 3.6 ARCHAEOLOGY AND CULTURAL HERITA
- Page 54: KEY:Scheme BoundaryScheduled Monume
- Page 57 and 58: LAQM TG (09) (1) , detailed assessm
- Page 59 and 60: Site Location OS grid ref Nature of
- Page 61 and 62: • A new deal for trunk roads in E
- Page 63 and 64: hrs), the noise level outside the n
- Page 65 and 66: Methodology and Evaluation Criteria
- Page 67 and 68: 4.3.3 Therefore the key elements fo
- Page 69 and 70: Evaluation Criteria4.3.7 Impacts up
- Page 71 and 72: Evaluation of Magnitude of Change4.
- Page 73 and 74: Table 4.8 Levels Significance of Vi
- Page 75 and 76: 4.4.6 Protected species recorded du
- Page 77 and 78: any predicted significant adverse i
- Page 79 and 80: 4.5.12 Impacts graded as minor stil
- Page 81 and 82: Criteria for Appraisal of Magnitude
- Page 83 and 84: Baseline Conditions4.7.6 Sources of
- Page 85 and 86: Subject AreaSignificance of EffectS
- Page 87 and 88: • records held by the British Geo
- Page 89 and 90: and transparent assessment of the
- Page 91 and 92: Box 5.1Proposed Structure of the ES
- Page 94 and 95: Proposed Consultation List for Scop
- Page 96: Annex BCode of Construction Practic
- Page 99 and 100: B7.1 DUST AND OTHER AIR POLLUTION 2
- Page 101 and 102: B1.2 PURPOSE AND AIMS OF THE CODE O
- Page 103 and 104:
Relevant Local AuthorityB1.6.4The r
- Page 105 and 106:
B2.5 COMPLAINTS LOGB2.5.1B2.5.2All
- Page 107 and 108:
B4SITE ARRANGEMENTSB4.1 SITE HOUSEK
- Page 109 and 110:
B4.2.2 More details of noise mitiga
- Page 111 and 112:
B4.6 LIVING ACCOMMODATIONB4.6.1No l
- Page 113 and 114:
B4.10.4B4.10.5In joint names with t
- Page 115 and 116:
B5.2.8B5.2.9B5.2.10B5.2.11B5.2.12Un
- Page 117 and 118:
B5.2.15B5.2.16B5.2.17Every reasonab
- Page 119 and 120:
Vehicle EmissionsCompliance to Stan
- Page 121 and 122:
B6NOISE AND VIBRATIONB6.1 NOISE CON
- Page 123 and 124:
vi)vii)viii)ix)use earth bunds (mad
- Page 125 and 126:
B7DUST AND AIR POLLUTIONB7.1 DUST A
- Page 127 and 128:
B7.1.14B7.1.15B7.1.16B7.1.17B7.1.18
- Page 129 and 130:
iiiiiiivvcarry out appropriate site
- Page 131 and 132:
B9PROTECTION OF THE WATER ENVIRONME
- Page 133 and 134:
B9.3.5Sanitary facilities will be p
- Page 135 and 136:
• Equipment and chemicals will be
- Page 137 and 138:
B9.10.1B9.10.2Specific method state
- Page 139 and 140:
B10ECOLOGYB10.1 ENCROACHMENT INTO W
- Page 141 and 142:
B10.4.1B10.4.2B10.4.3The ES has ide
- Page 143 and 144:
B10.4.14B10.4.15B10.4.16A further b
- Page 145 and 146:
B10.5.5B10.5.6Woody material genera
- Page 147 and 148:
B11ARCHAEOLOGY AND CULTURAL HERITAG
- Page 149 and 150:
B12LANDSCAPE AND VISUALB12.1.1The C
- Page 152 and 153:
C1INTRODUCTIONAs discussed in Chapt
- Page 154 and 155:
Figure C1Three Rail Corridor Option
- Page 156 and 157:
The case for re-opening the railway
- Page 158:
C1.3 NORTHERN CORRIDOR - DETAILED A
- Page 162 and 163:
The benefit of a Parkway station at
- Page 164 and 165:
allows easy interchange with Kidlin
- Page 166 and 167:
Table C1Key Station Option Decision
- Page 168 and 169:
Site Options Reason for Selection/R
- Page 170 and 171:
The key decisions were at the follo
- Page 172:
Name: College Farm No. 2OS Grid Ref
- Page 175 and 176:
overbridge at approx. 24m07ch toget
- Page 177 and 178:
land exists and crossing islittle u
- Page 179 and 180:
Railway Ref.:Type:Proposal:Name:OS
- Page 182:
CONTENTSD1 INTRODUCTION 1D2 EXISTIN
- Page 185 and 186:
D2EXISTING CONDITIONSD2.1 BASELINE
- Page 187 and 188:
train each day to Calvert has been
- Page 189 and 190:
Table D2.3Summary of Baseline Noise
- Page 191 and 192:
MeasurementPosition9 Residentialpro
- Page 193 and 194:
Table D2.5 Unattended Night-Time Me
- Page 195 and 196:
Table D2.7 Unattended Measurement S
- Page 197 and 198:
D3CONSTRUCTION NOISED3.1.1OverviewT
- Page 199 and 200:
D3.1.3Construction Plant Inventorie
- Page 201 and 202:
Table D3.5Plant Inventory Represent
- Page 203 and 204:
Plant Teams Number of Plant Require
- Page 205 and 206:
D4.1.4 Planning Policy Guidance Not
- Page 207 and 208:
D4.1.6Institute of Environmental Ma
- Page 209 and 210:
Chiltern Railways trainsDuring phas
- Page 211 and 212:
oute as well as specific speed limi
- Page 213 and 214:
D5.3.4Train SpeedsLine speeds defin
- Page 215 and 216:
D5.5 MEASUREMENT SURVEYSD5.5.1Noise
- Page 217 and 218:
D6GLOSSARY OF ACOUSTIC TERMSDecibel
- Page 220:
Annex ELandscape and VisualImpact
- Page 223 and 224:
A420A4129A4010Area 108 boundaryAdja
- Page 225 and 226:
Significant archaeological features
- Page 227 and 228:
The Vale of White Horse passes east
- Page 230:
Annex FEcologyAnnex F1: HRASAnnex F
- Page 234:
CONTENTSF1ANNEX F1- HABITATS REGULA
- Page 237 and 238:
F1.2 AIM OF THE REPORTThe aim of th
- Page 239 and 240:
F3BASELINEF3.1 EUROPEAN SITES AND S
- Page 241 and 242:
Table 3.1European Site and SSSI Inf
- Page 243 and 244:
Site name/area/distance fromdevelop
- Page 245 and 246:
Site name/area/distance fromdevelop
- Page 247 and 248:
Site name/area/distance fromdevelop
- Page 249 and 250:
Site name/area/distance fromdevelop
- Page 251 and 252:
Nutrient enrichment from pollutants
- Page 253 and 254:
oooooOxford Meadows SAC and 4 compo
- Page 256 and 257:
Chiltern Rail breeding bird survey:
- Page 258 and 259:
Chiltern Rail breeding bird survey:
- Page 260 and 261:
Access was not obtained for Wolverc
- Page 262 and 263:
Results and assessmentThe survey id
- Page 264 and 265:
Moorhen 4prs 3prs 1pr 1pr 1pr 1pr 5
- Page 266 and 267:
● House Sparrow 5prs 5prs 10 3prs
- Page 268 and 269:
Summary of the results for each sur
- Page 270 and 271:
There were four UK BAP species. The
- Page 272 and 273:
This is a very large area of open g
- Page 274 and 275:
There were five UK BAP species: dun
- Page 276 and 277:
In addition, many species, such as
- Page 278:
Annex F3Bats
- Page 281 and 282:
ERMChiltern LineBat Dusk and Dawn S
- Page 283 and 284:
Chiltern Line September 2009Bat Dus
- Page 285 and 286:
Chiltern Line September 2009Bat Dus
- Page 287 and 288:
Chiltern Line September 2009Bat Dus
- Page 289 and 290:
Chiltern Line September 2009Bat Dus
- Page 291 and 292:
Chiltern Line September 2009Bat Dus
- Page 293 and 294:
Chiltern Line September 2009Bat Dus
- Page 295 and 296:
Chiltern Line September 2009Bat Dus
- Page 297 and 298:
Chiltern Line September 2009Bat Dus
- Page 299 and 300:
Chiltern Line September 2009Bat Dus
- Page 364 and 365:
Chiltern Line September 2009Bat Dus
- Page 366:
Chiltern Line September 2009Bat Dus
- Page 370 and 371:
F4-1 ANNEX F4F4-1.1INTRODUCTIONERM
- Page 372 and 373:
Waterbodies not Considered for the
- Page 374 and 375:
In each case, this decision was onl
- Page 376 and 377:
estimated population size of great
- Page 378 and 379:
Further permanent waterbodies inclu
- Page 380 and 381:
Ponds GCN PresentSurvey that Record
- Page 382 and 383:
ERMChiltern Line, OxfordGreat Crest
- Page 384 and 385:
Chiltern Line, Oxford April 2009Gre
- Page 386 and 387:
Chiltern Line, Oxford April 2009Gre
- Page 389:
Chiltern Line, Oxford April 2009Gre
- Page 402:
ERM Great Crested Newt Habitat Suit
- Page 405 and 406:
Figure 3.2 Pond 6Figure 3.3 Pond 7
- Page 407 and 408:
Figure 3.6Pond 9bFigure 3.7 Pond 10
- Page 409 and 410:
Figure 3.10Pond 13aFigure 3.11Pond
- Page 411 and 412:
Figure 3.14Pond 18aFigure 3.15Pond
- Page 413 and 414:
Figure 3.18 Pond 23Figure 3.19Pond
- Page 415 and 416:
Figure 3.22 Pond 35Figure 3.23 Pond
- Page 417 and 418:
Figure 3.26Pond 42bFigure 3.27 Pond
- Page 419 and 420:
Figure 3.30Pond 45bFigure 3.31Pond
- Page 421 and 422:
Great Crested Newt Presence Survey
- Page 423 and 424:
Great Crested Newt Presence Survey
- Page 425 and 426:
Great Crested Newt Presence Survey
- Page 427 and 428:
Great Crested Newt Presence Survey
- Page 429 and 430:
Great Crested Newt Presence Survey
- Page 431 and 432:
Great Crested Newt Presence Survey
- Page 433 and 434:
Great Crested Newt Presence Survey
- Page 435 and 436:
Great Crested Newt Presence Survey
- Page 437 and 438:
Great Crested Newt Presence Survey
- Page 439 and 440:
Great Crested Newt Presence Survey
- Page 441 and 442:
Great Crested Newt Presence Survey
- Page 443 and 444:
Great Crested Newt Presence Survey
- Page 445 and 446:
Great Crested Newt Presence Survey
- Page 447 and 448:
Great Crested Newt Presence Survey
- Page 449 and 450:
Great Crested Newt Presence Survey
- Page 451 and 452:
Great Crested Newt Presence Survey
- Page 453 and 454:
Great Crested Newt Presence Survey
- Page 455 and 456:
Great Crested Newt Presence Survey
- Page 458:
Annex F5Otter and Water Vole
- Page 461 and 462:
ERMChiltern Line, Oxford - Bicester
- Page 463 and 464:
Chiltern Line, Oxford - Bicester Au
- Page 465 and 466:
Chiltern Line, Oxford - Bicester Au
- Page 467 and 468:
Chiltern Line, Oxford - Bicester Au
- Page 469 and 470:
Chiltern Line, Oxford - Bicester Au
- Page 471 and 472:
Chiltern Line, Oxford - Bicester Au
- Page 473 and 474:
Chiltern Line, Oxford - Bicester Au
- Page 492 and 493:
Chiltern Line, Oxford - Bicester Au
- Page 494 and 495:
Chiltern Line, Oxford - Bicester Au
- Page 496:
Annex F6Badgers - CONFIDENTIAL
- Page 500 and 501:
ERMChiltern LineReptile ReportSepte
- Page 502 and 503:
Chiltern Line September 2009Reptile
- Page 504 and 505:
Chiltern Line September 2009Reptile
- Page 506 and 507:
Chiltern Line September 2009Reptile
- Page 508 and 509:
Chiltern Line September 2009Reptile
- Page 510 and 511:
Chiltern Line September 2009Reptile
- Page 512 and 513:
Chiltern Line September 2009Reptile
- Page 514 and 515:
Chiltern Line September 2009Reptile
- Page 532 and 533:
Chiltern Line September 2009Reptile
- Page 534 and 535:
Chiltern Line September 2009Reptile
- Page 536 and 537:
Chiltern Line September 2009Reptile
- Page 538:
Annex GWater Resources andFlood Ris
- Page 542 and 543:
G1ANNEX I: LEGISLATION AND POLICY C
- Page 544 and 545:
classes: RE1 (high quality) to RE5
- Page 546 and 547:
supplies. Within SPZs there are inn
- Page 548 and 549:
Catchment Flood Management Plans: V
- Page 550:
G1.13 POLLUTION PREVENTION GUIDELIN
- Page 554:
Wallingford HydroSolutions LtdChilt
- Page 557 and 558:
Contents1 Introduction.............
- Page 559 and 560:
1 Introduction1.1 OverviewThis Floo
- Page 561 and 562:
information. SFRA Flood Zones there
- Page 563 and 564:
Assessment Point Name Description o
- Page 565 and 566:
Figure 22.3 AP2 - Tubbs Lane Footbr
- Page 567 and 568:
Figure 42.5 AP4 - A41 OverbridgeThe
- Page 569 and 570:
Figure 62.7 AP6 - Elm Tree Farm/Lan
- Page 571 and 572:
Figure 82.9 AP8 - Holts Farm Overbr
- Page 573 and 574:
Figure 102.11 AP10 - Oddington Over
- Page 575 and 576:
treated as a permeable structure, a
- Page 577 and 578:
Figure 142.15 AP14 - Water Eaton Pa
- Page 579 and 580:
Figure 162.17 AP16 - Wolvercot Tunn
- Page 581 and 582:
Figure 182.19 AP18 - Sheepwash Brid
- Page 583 and 584:
Figure 2025
- Page 585 and 586:
3.3 The Requirements of the Excepti
- Page 587 and 588:
The existing EA Flood Map of the ar
- Page 589 and 590:
3.5.4 AP5 - OXD40 UnderbridgeThe de
- Page 591 and 592:
It is proposed that the current pro
- Page 593 and 594:
The site is on previously-developed
- Page 595 and 596:
Table 1 Summary of AssessmentsAsses
- Page 597 and 598:
4 Surface Water Runoff Assessments4
- Page 599 and 600:
Table 2 Current and post developmen
- Page 601 and 602:
4.3 SUDS Design CommitmentsThe prev
- Page 603 and 604:
6 ReferencesAtkins (2008). Oxford C
- Page 605 and 606:
climate change allowance for the pe
- Page 608 and 609:
H1BIBLIOGRAPHY AND LIST OF SOURCES
- Page 610 and 611:
H2GAZETTEER OF DESIGNATED SITESA li
- Page 612 and 613:
OARef.NoFeatureType19 ListedBuildin
- Page 614 and 615:
OA Feature Type Description SourceR
- Page 616 and 617:
OA Feature Type Description SourceR
- Page 618 and 619:
OA Feature Type Description SourceR
- Page 620 and 621:
OA Feature Type Description SourceR
- Page 622 and 623:
OARef. No254 ArchaeologicalInvestig
- Page 624 and 625:
OARef. No266 ArchaeologicalInvestig
- Page 626 and 627:
OARef. No297 ArchaeologicalInvestig
- Page 628 and 629:
OA Feature Type Description SourceR
- Page 630 and 631:
OA Feature Type Description SourceR
- Page 632:
188G10935110#194195G189- X:\Oxford
- Page 636:
Annex ITraffic and TransportAnnex I
- Page 640:
NLaunton RoadStation ApproachBicest
- Page 644:
Annex I2Bus Capacity Survey
- Page 647 and 648:
Bus Capacity SurveyService 2/2A/2B/
- Page 649 and 650:
Bus Capacity SurveyService 7A/7B -
- Page 651 and 652:
Bus Capacity SurveyService S5 - PM
- Page 653 and 654:
Bus Capacity SurveyService 500 - PM
- Page 655 and 656:
Bus Capacity SurveyService 700 - PM
- Page 657 and 658:
Bicester Bus Capacity SurveyService
- Page 659 and 660:
Bicester Bus Capacity SurveyService
- Page 668:
Annex I4Proposed ConstructionRoutei
- Page 672:
NMILLSTREAM VIADUCT RECONSTRUCTIONS
- Page 676:
Parking AccumulationWater Eaton and
- Page 686:
Annex I7S-Paramics Model Outputs:Wa
- Page 689 and 690:
09:5009:4009:3009:2009:1009:0008:50
- Page 691 and 692:
18:5018:4018:3018:2018:1018:0017:50
- Page 693 and 694:
18:5018:4018:3018:2018:1018:0017:50
- Page 695 and 696:
450Average Journey Time for Soutbou
- Page 697 and 698:
450Average Journey Time for Northbo
- Page 700 and 701:
J1INTRODUCTIONChapter 13 of the ES
- Page 702 and 703:
ENVIRONMENTAL RESOURCES MANAGEMENTC
- Page 704 and 705:
Table J2.1 Additional Train Movemen
- Page 706 and 707:
J2.3.4Other Modelling InputsThe exh
- Page 708 and 709:
Water Eaton:A4165 (Banbury Road)A41
- Page 710 and 711:
Table J3.4Change in Traffic Flows F
- Page 712:
Table J4.3 Conversion Factors from
- Page 716 and 717:
K1.1 ANNEX KThis Annex provides det
- Page 718:
Annex LLand Quality
- Page 721 and 722:
Table L3Ranking Assessment of Poten
- Page 723 and 724:
Human Health Groundwater Surface Wa