COMFLTFORCOMINST 4790.3 REV A CH-1<br />

3.3.15 Shipboard Crane Certification Program (CVN/MHC/LHD/LPD/LSD only). The Shipboard Crane<br />

Certification Program established by reference (aa) is intended to improve the reliability and safety of all shipboard<br />

cranes and is applicable to all cranes mounted on board. Initial crane certification should be accomplished per<br />

reference (aa).<br />

3.4 <strong>MAINTENANCE</strong> AND MATERIAL MANAGEMENT PROGRAM.<br />

3.4.1 Planned Maintenance System.<br />

a. The installation of the Planned Maintenance System (PMS) on new construction ships should be<br />

scheduled to provide maintenance documentation to support the Operational Control Transfer (OCT) of<br />

systems/equipments from the shipbuilder to Ship's Force. This early loadout of PMS allows Ship's<br />

Force personnel to become familiar with the maintenance procedures and facilitates the identification of<br />

problems with the Maintenance Requirement Cards (MRC) prior to the ship being placed in operation.<br />

Local RMC coordinates the scheduling of PMS installations with the ship's Maintenance and Material<br />

Management (3-M) Coordinator. In addition, local RMC is responsible for:<br />

(1) Generating a preliminary List of Effective Pages (LOEP) for Phase I validation.<br />

(2) Conducting Phase I of the PMS installation.<br />

(3) Generating a final LOEP based on Phase I and 3-M Coordinator Feedback.<br />

(4) Notifying local RMC of the required PMS documentation (LOEP requirements) and the date<br />

the documentation is required to support Phase II PMS installation.<br />

(5) Compile Phase II PMS package and forward to ship.<br />

(6) Conduct Phase II PMS installation.<br />

(7) Effect additional LOEP corrections as a result of Phase II.<br />

(8) Outbrief with ship's PCO/OIC concerning status of ship's 3-M program.<br />

b. PMS installation for nuclear powered ships will be conducted approximately six months prior to initial<br />

reactor plant criticality. The installation for non-nuclear ships will be conducted at least three months<br />

prior to delivery. Installation of PMS is accomplished in two phases.<br />

(1) Phase I. Phase I results in the establishment of a ship's LOEP. Local RMC, utilizing either the<br />

LOEP from the previous ship of the class or configuration information provided by Submarine<br />

Maintenance Engineering, Planning and Procurement (SUBMEPP) Activity (Submarines<br />

only), Supervisor of Shipbuilding Newport News (SUPSHIP NN), Code 1800, (Nuclear<br />

Powered Aircraft Carriers only) or applicable TYCOM (other Surface Ships only), generates a<br />

preliminary LOEP for Ship's Force review. This preliminary LOEP and copies of the listed<br />

Maintenance Index Pages (MIP) are delivered to the new construction unit for a review by the<br />

ship's 3-M Coordinator, Work Center Supervisors and maintenance personnel. Ship's Force<br />

personnel review the documentation, verify MIP to Work Center assignments and approve the<br />

preliminary LOEP. Phase I occurs approximately two months prior to Phase II.<br />

I-3-10