REFERENCES.<br />

VOLUME I<br />

CHAPTER 6<br />

POST SHAKEDOWN AVAILABILITY<br />

COMFLTFORCOMINST 4790.3 REV A CH-2<br />

(a) OPNAVINST 4700.8 - Trials, Acceptance, Commissioning, Fitting Out, Shakedown, and Post<br />

Shakedown Availability of U.S. Naval Ships Undergoing Construction or Conversion<br />

(b) NAVSO P 1000 - Navy Comptroller Manual<br />

(c) OPNAVINST 9110.1 - Policy Concerning Submarine Test and Operating Depths<br />

(d) NAVSEAINST 4790.8/OPNAVINST 4790.4 - Ships' Maintenance and Material Management (3-M)<br />

Manual<br />

(e) INSURVINST 4730.11 - Preparation of Deficiency Forms<br />

(f) OPNAVINST 3540.3 - Naval Nuclear Propulsion Examining Boards<br />

(g) COMSUBLANT/COMSUBPACINST C3500.1 - Submarine Force Training Manual<br />

(h) COMNAVSUBFOR OPORD 2000<br />

(i) NAVSEAINST C9094.2 - Submarine Valve Operation Requirements for Builders and Post-Overhaul<br />

Sea Trial Test Dives<br />

(j) NAVSEA S9086-DA-STM-000 - NSTM Chapter 100 (Hull Structures)<br />

LISTING OF APPENDICES.<br />

A Major Funding Milestones During Construction/Conversion<br />

B Post Shakedown Availability Planning Events Milestone Schedule<br />

C Summary of Major Milestones for Post Shakedown Availability<br />

D Minimum Post Shakedown Availability Sea Trial Requirements for a Submarine Deep Dive<br />

6.1 PURPOSE.<br />

a. Post Shakedown Availability (PSA) is an industrial activity availability assigned to correct deficiencies<br />

found during the shakedown cruise or to accomplish other authorized improvements. PSAs are<br />

scheduled to commence after delivery and to be completed prior to the Shipbuilding and Conversion,<br />

Navy (SCN) obligation work limiting date. This date occurs at the end of the 11th month after the<br />

month in which the Fitting Out Period completed for surface units or at the end of the 11th month after<br />

the month in which delivery occurs for submarines. Appendix A of this chapter, taken from reference<br />

(a), reflects the Major Milestones during Construction related to funding. Funding guidelines for PSA<br />

are outlined in reference (b).<br />

b. The length of time designated for PSAs will vary dependent on the platform. Acceptance Trial (AT),<br />

Final Contract Trial (FCT), Combined Trial (CT) and Guarantee Material Inspection (GMI) related<br />

deficiencies constitute the majority of the PSA workload. Ship Program Manager planned, authorized<br />

and funded modifications may also be included.<br />

I-6-1