Time Event<br />

COMFLTFORCOMINST 4790.3 REV A<br />

90 a. Ship Program Manager issue final list of SCN funded items authorized for accomplishment<br />

during PSA.<br />

100 a. Supervising Authority issue final PSA work package.<br />

149 a. Pre-Arrival Conference:<br />

(1) Purpose - To review all work authorized by all customers with available cost estimates<br />

and to establish arrival procedures and conditions for the ship. Review and take action<br />

on Post Delivery Deficiency Items (PDDI).<br />

(2) Participants - Ship Program Manager, Supervising Authority, Shipbuilder, TYCOM,<br />

ISIC and Ship.<br />

154 a. Commence PSA.<br />

b. Arrival Conference (Ship Program Manager and TYCOM participation not required unless<br />

specifically requested).<br />

214-274 a. End PSA. (Completion date varies with platform).<br />

*<br />

**<br />

a. Ship submit final status report of all deficiencies (Departure Report).<br />

a. TYCOM comment on final status report from ship and submit recommendations for Ship<br />

Program Manager action.<br />

b. TYCOM issue follow-up letter requesting Ship Program Manager final resolution and action on<br />

government responsible uncorrected deficiencies.<br />

*** a. Work limiting date for SCN appropriation.<br />

* 30 days after completion of PSA<br />

** 45 days after completion of PSA<br />

*** Refer to Appendix A of this chapter, Note (1)<br />

I-6B-3