COMFLTFORCOMINST 4790.3 REV A CH-2<br />

5.2 DEFICIENCY CORRECTION. Deficiencies are addressed in terms of three general categories. The procedure<br />

for initiating corrective action for a deficiency is determined by the category.<br />

5.2.1 Government Responsible Items. The obligation and work limiting date for all shipbuilding programs under<br />

the SCN appropriation will normally be at the end of the 11th month following completion of the fitting out period.<br />

For submarines, the fitting out period ends at delivery. Government responsible work accomplished in support of a<br />

new construction ship and funded under SCN is limited to work which can be completed prior to the end of this 11<br />

month period. Authorization for correction of non-reactor plant government responsible deficiencies is provided by<br />

the Ship Program Manager based on a priority assignment by the ship and recommendations from the Type<br />

Commander (TYCOM). Authorization for correction of reactor plant government responsible deficiencies is<br />

provided by NAVSEA Nuclear Propulsion Directorate (08).<br />

5.2.2 Shipbuilder Responsible Items. Construction contracts with private industrial activities contain a guarantee<br />

clause. The rights of the government concerning deficiencies identified during the guarantee period are set forth in<br />

the contract. Deficiencies must be identified and reported to the shipbuilder and cognizant government agencies<br />

prior to the end of the guarantee period in order for corrective action to be established. Correction of deficiencies<br />

designated shipbuilder responsible can be accomplished during any subsequent period that the ship is made available<br />

to the shipbuilder. Availability of the ship is usually limited to the Post Shakedown Availability (PSA), except<br />

under special circumstances when immediate corrective action prior to PSA is required to permit the ship to meet<br />

operational commitments. The ship may also be made available to the shipbuilder after PSA to permit follow-up<br />

corrective action on shipbuilder responsible deficiencies identified during the guarantee period but not satisfactorily<br />

corrected during PSA.<br />

5.2.3 Recommended Changes in Characteristics, Design Specifications, or Plans. Improvements to the ship<br />

recommended by INSURV will be investigated by the Ship Program Manager. Action, as appropriate, will be<br />

initiated by a government approved change. This change may be in the form of a Field Modification Request<br />

(FMR), Headquarters Modification Request (HMR), Ship Alteration (SHIPALT), Ordnance Alteration (ORDALT),<br />

Strategic Systems Programs Alteration (SPALT), Service Change, Machinery Alteration (MACHALT) and Field or<br />

Engineering Change Proposal. Changes of this nature usually have application to more than one ship of the class.<br />

Improvements to the ship recommended by Ship's Force should be forwarded by the CO in accordance with Volume<br />

VI, Chapter 3 of this manual to the Ship Program Manager via the Supervising Authority.<br />

5.3 REQUIRED REPORTS. The responsibility for ensuring deficiencies are corrected rests jointly with the CO,<br />

the Supervising Authority and the Ship Program Manager. The method of corrective action varies with the type of<br />

deficiency and may involve the coordinated action of several activities. In order to effectively prosecute each<br />

deficiency, special reporting and handling procedures are necessary. The Ship's Maintenance Data System shall be<br />

implemented not later than delivery in accordance with reference (a). This will provide a smooth transition into the<br />

Maintenance Resources Management System (MRMS) and permit Maintenance and Material Management (3-M)<br />

documentation of all INSURV deficiencies for use with the Consolidated Report. The Consolidated Report provides<br />

follow-up action on all deficiencies and minimizes administrative effort.<br />

a. Consolidated Report. A Consolidated Report, compiled by the Ship Program Manager, combines into<br />

one document the screening actions, reports of completed actions and significant information as listed<br />

below (as applicable):<br />

(1) AT/CT INSURV Report.<br />

(2) FCT/GMI INSURV Report.<br />

(3) Post Delivery Deficiency Items (PDDI).<br />