COMFLTFORCOMINST 4790.3 REV A CH-1<br />

Time Event<br />

27 a. PSA Planning Conference.<br />

(1) Purpose - To establish PSA work package from input to date and to identify required<br />

advance planning actions.<br />

(2) Participants - Ship Program Manager, Supervising Authority, TYCOM, Ship and<br />

Shipbuilder.<br />

30 a. Ship submit priority list of AT/CT deficiencies.<br />

35 a. TYCOM comments on ship's priority list.<br />

40 a. Ship Program Manager issue list of SCN funded items authorized for accomplishment during<br />

PSA.<br />

42 a. TYCOM assign Restricted Availability.<br />

45 a. Supervising Authority issue initial PSA work package.<br />

b. (Submarines only) Latest date for the conduct of Ship Program Manager sponsored Acoustic and<br />

Combat System Certification Trials in order to present to the INSURV Board at the GMI.<br />

50 a. Prepare for FCT/GMI in accordance with reference (d).<br />

b. TYCOM representative places ship in "INSURV Window" and calls down ship's Pre-INSURV<br />

Package.<br />

54 a. FCT/GMI by the INSURV Board.<br />

b. Conference following FCT/GMI critique (may coincide with Planning or Pre-Arrival<br />

Conference).<br />

(1) Purpose - To assign responsibility for correction of deficiencies and to assign<br />

ship/TYCOM priorities.<br />

(2) Participants - Ship Program Manager, Supervising Authority, Shipbuilder, TYCOM,<br />

Ship, and ISIC (optional).<br />

c. Ship Program Manager issue Section B of Consolidated Report.<br />

d. Ship comply with reference (d) for documenting INSURV items.<br />

75 a. (Submarines only) Silencing Deficiency Conference:<br />

(1) Purpose - Naval Surface Warfare Center Carderock Division (NSWCCD) presents<br />

results of acoustic trials data analysis.<br />

(2) Participants - NSWCCD, Ship Program Manager, Shipbuilder, TYCOM, Ship.<br />

I-6B-2