23.03.2013 Views

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

1<br />

2<br />

3<br />

4<br />

5<br />

6<br />

7<br />

8<br />

9<br />

10<br />

11<br />

12<br />

13<br />

14<br />

15<br />

16<br />

17<br />

18<br />

19<br />

20<br />

21<br />

22<br />

23<br />

24<br />

<strong>FortisBC</strong> <strong>Inc</strong>. (<strong>FortisBC</strong> or the Company)<br />

<strong>Application</strong> <strong>for</strong> a <strong>Certificate</strong> <strong>of</strong> <strong>Public</strong> Convenience and Necessity<br />

<strong>for</strong> the Advanced Metering Infrastructure Project<br />

Response to British Columbia Utilities Commission (BCUC or the Commission)<br />

In<strong>for</strong>mation Request (IR) No. 1<br />

Submission Date:<br />

October 5, 2012<br />

Page 114<br />

First, the Company segmented the proposed AMI project into its major components, defining<br />

them in terms <strong>of</strong> component cost and percentage <strong>of</strong> total project cost.<br />

Each component was assessed against AACE guidelines (see the response to BCUC IR1,<br />

Q53.3 <strong>for</strong> reference) in order to determine the applicable estimate range. The proposed<br />

contingency <strong>for</strong> each component was then examined to determine if it made sense relative to<br />

the applicable AACE estimate guideline.<br />

In order to arrive at a reasonable “full project” AACE estimate, the last step was to group the<br />

components (excluding regulatory, PST, AFUDC, Capitalized Overhead and contingency costs)<br />

into the variously applicable AACE estimate categories. See below:<br />

As this demonstrates, while the bulk <strong>of</strong> the proposed project is AACE estimate 2 or better, there<br />

remains a material portion <strong>of</strong> the proposed project at Class 3 or 4.<br />

Response:<br />

53.5 What is included in the estimate?<br />

The estimate includes:<br />

• Capital costs covering hardware, s<strong>of</strong>tware, and the work required to implement<br />

them, including project management costs;<br />

• Project development and regulatory costs;<br />

• AFUDC;<br />

• PST;<br />

• Capitalized Overhead; and<br />

• An aggregate contingency <strong>for</strong> the whole project, as determined through the process