23.03.2013 Views

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

FortisBC Inc. (FortisBC) Application for a Certificate of Public ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

1<br />

2<br />

3<br />

4<br />

5<br />

6<br />

7<br />

8<br />

9<br />

10<br />

11<br />

12<br />

13<br />

14<br />

15<br />

16<br />

17<br />

18<br />

19<br />

20<br />

21<br />

22<br />

23<br />

24<br />

<strong>FortisBC</strong> <strong>Inc</strong>. (<strong>FortisBC</strong> or the Company)<br />

<strong>Application</strong> <strong>for</strong> a <strong>Certificate</strong> <strong>of</strong> <strong>Public</strong> Convenience and Necessity<br />

<strong>for</strong> the Advanced Metering Infrastructure Project<br />

Response to British Columbia Utilities Commission (BCUC or the Commission)<br />

43.0 Reference: Project Description<br />

Response:<br />

In<strong>for</strong>mation Request (IR) No. 1<br />

Exhibit B-1, Tab 4.0, Sec. 4.3.5, p. 57<br />

Project Risk and Mitigation<br />

Submission Date:<br />

October 5, 2012<br />

Page 80<br />

43.1 In financial terms, what is the impact on NPV and Rates <strong>of</strong> a delay in operational<br />

benefits <strong>of</strong> the AMI Project (ie., meter reading, theft reduction, etc.) <strong>of</strong> six<br />

months?<br />

In this response, <strong>FortisBC</strong> assumes that the proposed AMI project is implemented as per the<br />

preliminary project plan, but operational benefits are delayed by six months.<br />

Delays in operational benefits related to meter reading, remote disconnect/reconnect, contact<br />

centre, and theft reduction were included in the analysis.<br />

The Company did not include meter exchanges or avoided cost benefits associated with<br />

Measurement Canada compliance, since those benefits are realized by the installation <strong>of</strong> the<br />

AMI meters.<br />

See the table below <strong>for</strong> the financial impact <strong>of</strong> a six month delay in the realization <strong>of</strong> the stated<br />

operational benefits:<br />

AMI proposal (errata 1)<br />

NPV ($000s)<br />

6 month delay in<br />

operational benefits<br />

Meter Reading -$23,785 -$22,383<br />

Remote<br />

Disconnect/Reconnect -$5,466 -$5,158<br />

Contact Centre -$441 -$410<br />

Theft Reduction -$38,386 -$37,491<br />

Project NPV -$17,629 -$14,992<br />

44.0 Reference: Project Description<br />

Exhibit No. B-1, Tab 4.0, Section 4.3.2, p. 59<br />

Schedule