15. Upon completion of the detailed consolidated Contract Documents, including the incorporation of changes as<br />

required in conjunction with the final technical review, the Consultant shall submit the composite Contract Document<br />

package to the Commissioner <strong>for</strong> review <strong>and</strong> approval. This submission shall include, but not be limited to the following:<br />

a) The original of the title sheet, signed by the Consultant, prepared in a <strong>for</strong>mat as approved by the<br />

Commissioner.<br />

b) A set of paper prints of the Contract Drawings.<br />

c) A copy of the Project Fact Sheet prepared in the currently required Departmental <strong>for</strong>mat.<br />

16. The signature of the Commissioner on the title sheet of the Contract Drawings shall constitute approval of the<br />

Design.<br />

17. Upon approval of the Contract Documents, the Consultant shall prepare <strong>and</strong> submit to the Commissioner, the<br />

complete Bid-Ready package of the Contract Documents. This package shall include the appropriate number of copies, as<br />

outlined in Section 2.5 of these General Requirements, of the following: complete, bound, signed Contract Drawings;<br />

complete, unbound Contract Specifications, Addenda <strong>and</strong> Bid Schedule Sheets; Composite Scope Packet; <strong>and</strong> approvals<br />

<strong>and</strong> permits required <strong>for</strong> the prosecution of the ensuing construction contract; all as required under the various tasks<br />

included in the Specific Requirements of this Contract.<br />

18. The Consultant shall make no substantial changes to the Final Contract Documents, as approved by the<br />

Commissioner, unless specifically ordered to do so by the Commissioner.<br />

(a)<br />

Study <strong>and</strong> Design of Street Grades<br />

Under this subsection the Consultant shall study the existing grades <strong>and</strong> <strong>design</strong> proposed grades <strong>for</strong> the project's<br />

roadway(s), sidewalks, <strong>and</strong> intersection(s) including intersecting roadway(s) <strong>and</strong> sidewalks in accordance with the <strong>design</strong><br />

criteria provided by the Commissioner or recommended by the Consultant <strong>and</strong> accepted by the Commissioner. The<br />

Consultant shall:<br />

a) Where the topographic survey is to be provided under this Contract:<br />

(i) Coordinate with the Surveyor, as appropriate, the integration of project topographic survey work with<br />

project grade <strong>design</strong> work in accordance with the project <strong>design</strong> needs <strong>and</strong> approved project schedule;<br />

(ii) Be solely responsible to coordinate, with the surveyor, the quantity <strong>and</strong>/or location of spot elevations <strong>and</strong><br />

profiles to be produced, <strong>and</strong> shall "customize" the data gathering to "specifically" satisfy the <strong>design</strong><br />

<strong>requirements</strong> <strong>for</strong> all grade <strong>design</strong>;<br />

b) Utilize existing topographic data to the extent necessary <strong>for</strong> the proper completion of this task;<br />

c) Analyze in detail <strong>and</strong> <strong>design</strong> "best fit" project grades <strong>for</strong> top of curb, back of sidewalk, building line, fence line,<br />

or other grade control points or profiles with a view to minimizing negative impacts on adjacent development,<br />

adjacent properties (driveways, walkways, loading docks, parking areas, building entrances, steps, underground<br />

structures <strong>and</strong>/or infrastructure, plant life - including trees), while providing <strong>for</strong> adequate roadway <strong>and</strong> property<br />

drainage, adequate sidewalk cross slopes <strong>and</strong> the <strong>design</strong> of measures needed to mitigate such impacts.<br />

d) Develop/<strong>design</strong> project sidewalk cross slopes upon completion of a review of the project profiles in compliance<br />

with the <strong>requirements</strong> of the Americans with Disabilities Act Accessibility Guidelines (ADAAG) - specifically<br />

providing, where feasible, a continuous path having a 2% maximum cross slope with ramps having a maximum<br />

longitudinal slope of 5%, to the maximum extent possible in the <strong>design</strong> of curb <strong>and</strong> sidewalk grades;<br />

e) Provide both graphic exhibit(s) <strong>and</strong> text to justify all "site infeasibilities". Prepare a final Americans with<br />

Disabilities Act Accessibility Guidelines "site infeasibility" justification report <strong>for</strong> all properties/locations that will have<br />

non-con<strong>for</strong>ming sidewalks, in a <strong>for</strong>mat determined by the City. The report shall document in tabular, graphic <strong>and</strong>/or<br />

other preapproved <strong>for</strong>mat the location, nature, extent <strong>and</strong> justification <strong>for</strong> all locations at which, in the judgment of<br />

NYC Department of Design <strong>and</strong> Construction<br />

Infrastructure, October 2012<br />

GR-50