4.4 Final Task Order: Following the process set <strong>for</strong>th above, the Commissioner shall issue a Task Order to the<br />

Consultant. The Commissioner may issue separate <strong>and</strong>/or supplementary Task Orders to the Consultant <strong>for</strong> the<br />

per<strong>for</strong>mance of <strong>services</strong> <strong>for</strong> different phases or portions of the Project, or <strong>for</strong> the per<strong>for</strong>mance of any portion or<br />

component of the <strong>services</strong> set <strong>for</strong>th in Article 6. Each Task Order issued hereunder shall specify the items set <strong>for</strong>th<br />

below:<br />

4.4.1 Description of the Project <strong>for</strong> which <strong>services</strong> are required<br />

4.4.2 Services to be per<strong>for</strong>med by the Consultant<br />

4.4.3 Method(s) of Payment <strong>for</strong> the per<strong>for</strong>mance of <strong>services</strong><br />

4.4.4 Requirements <strong>for</strong> scheduling <strong>and</strong>/or phasing of the <strong>services</strong><br />

4.4.5 Time frame <strong>for</strong> the completion of <strong>services</strong><br />

4.4.6 Overall Not to Exceed amount <strong>for</strong> the <strong>services</strong> to be per<strong>for</strong>med. Such overall Not to Exceed Amount<br />

shall be broken down into various amounts <strong>and</strong>/or allowances, depending on the required <strong>services</strong> <strong>and</strong><br />

the method(s) of payment specified in the Task Order. Such amounts <strong>and</strong>/or allowances may include<br />

the following: (1) Preliminary Design Fee, (2) Topographic Survey Fee, (3) Final Design Fee, (4)<br />

Allowance <strong>for</strong> Time Card Services, (5) Allowance <strong>for</strong> Artwork, <strong>and</strong> (6) Allowance <strong>for</strong> Reimbursable<br />

Services.<br />

4.5 Miscellaneous Provisions: The provision set <strong>for</strong>th below shall apply to Task Orders issued hereunder.<br />

4.5.1 Supplementary Task Orders: In the event of any changes to the Task Order, the Commissioner shall<br />

issue a Supplementary Task Order to the Consultant. The Consultant shall be bound by the terms <strong>and</strong> conditions of any<br />

such Supplementary Task Order issued by the Commissioner.<br />

4.5.2 Reallocation of Allowance Amounts: Notwithst<strong>and</strong>ing the specific amount allocated <strong>for</strong> allowances,<br />

as set <strong>for</strong>th in Task Orders issued hereunder, the Commissioner may, by issuance of a Supplementary Task Order to the<br />

Consultant, reallocate such specific allowance amounts; provided, however, a Supplementary Task Order is not required<br />

if the change in allowance amounts is due to a distribution of the contingency amount. Such change in allowance<br />

amount(s) shall be accompanied by a written directive to the Consultant.<br />

4.5.3 Conflicts: In the event of any conflict between a Task Order issued hereunder <strong>and</strong> any provision of<br />

this Contract, the Contract shall take precedence; except that with respect to the <strong>services</strong> to be per<strong>for</strong>med, the provisions<br />

of the Task Order shall take precedence over Article 6 of this Contract.<br />

4.5.4 No Right to Reject: The Consultant shall have no right (a) to decline to respond to an RFP, (b) to<br />

reject a Task Order issued hereunder, or (c) to decline to per<strong>for</strong>m <strong>services</strong> pursuant to a Task Order. Failure by the<br />

Consultant to respond to an RFP or to per<strong>for</strong>m <strong>services</strong> pursuant to a Task Order issued hereunder shall be grounds <strong>for</strong><br />

termination <strong>for</strong> cause.<br />

4.5.5 Work by Others: In the event there is a need <strong>for</strong> <strong>engineering</strong> <strong>design</strong> <strong>and</strong> <strong>related</strong> <strong>services</strong>, the<br />

Commissioner reserves the right not to utilize this <strong>requirements</strong> contract <strong>and</strong> to proceed with a new solicitation <strong>for</strong> the<br />

required <strong>services</strong>, or to have the <strong>services</strong> per<strong>for</strong>med by another consultant(s), or by City employees, if the<br />

Commissioner, in his/her sole opinion, determines that it would be in the best interest of the City to do so.<br />

ARTICLE 5<br />

The Consultant’s Personnel<br />

5.1 Provision of Personnel: The Consultant agrees, throughout the term of the Contract, to provide personnel <strong>for</strong><br />

the per<strong>for</strong>mance of all required <strong>engineering</strong> <strong>design</strong> <strong>and</strong> <strong>related</strong> <strong>services</strong> <strong>for</strong> the Project in accordance with Task Orders<br />

issued by the Commissioner. The Consultant shall provide such personnel through its own employees <strong>and</strong>/or through<br />

its Subconsultants, as set <strong>for</strong>th in Exhibit B, unless otherwise approved by the Commissioner. The Consultant<br />

specifically agrees that its employees, agents <strong>and</strong> Subconsultants shall possess the experience, knowledge <strong>and</strong> character<br />

necessary to qualify them individually <strong>for</strong> the particular duties they per<strong>for</strong>m.<br />

5.2 Key Personnel: The names of individuals identified as Key Personnel by the Consultant in its Proposal <strong>for</strong> the<br />

Contract, as well as their titles <strong>and</strong> qualifications, are set <strong>for</strong>th in Exhibit B. For specific Projects pursuant to this<br />

Contract, the Consultant expressly agrees to assign to such Projects <strong>for</strong> their entire duration, the individuals identified in<br />

_____________________________________________________________________________________________<br />

CITY OF NEW YORK<br />

4 ENGINEERING DESIGN AND RELATED SERVICES<br />

DEPARTMENT OF DESIGN AND CONSTRUCTION REQUIREMENTS CONTRACT (LRG) SEPT. 2012