Issue 1 Revision 2 (draft) - 25.07.2010<br />

GMES-GSEG-EOPG-TN-09-0008<br />

page 33 of 350<br />

In this respect, the perimeter of the <strong>Sentinel</strong>-2 <strong>PDGS</strong> system within the overall <strong>GSC</strong> is<br />

delimited as follows:<br />

○ On one side, it is delimited as a sub-system of the <strong>Sentinel</strong>-2 system responsible for<br />

payload planning, data acquisition and processing of the <strong>Sentinel</strong>-2 satellite data, while<br />

contributing to the overall monitoring of the payload and platform in coordination with<br />

the <strong>Sentinel</strong>-2 FOS.<br />

○ On the other side, it is delimited as a component of the <strong>GSC</strong> ground infrastructure,<br />

responsible for feeding <strong>Sentinel</strong>-2 data to the GSS as required by the DAP through the<br />

<strong>GSC</strong>DA similarly to any GCM. In addition to its strict role vis-à-vis the GSS, the scope<br />

of the <strong>Sentinel</strong>-2 <strong>PDGS</strong> is enlarged for the provision of <strong>Sentinel</strong>-2 data to the Users<br />

following the <strong>Sentinel</strong>-2 Data Policy.<br />

With respect to the <strong>GSC</strong>DA as and its sub-systems such as the CDS, the <strong>Sentinel</strong>-2<br />

<strong>PDGS</strong> is considered as a GCM infrastructure. As such, the <strong>PDGS</strong> contributes to the<br />

<strong>GSC</strong>DA by implementing its applicable interfaces vis-à-vis GCMs as relevant to<br />

<strong>Sentinel</strong>-2.<br />

On another side, the <strong>PDGS</strong> integrates <strong>ESA</strong>’s Multi-Mission User-Services (MMUS) for<br />

data cataloguing and access for the general User support services.<br />

Starting at Phase-E1 of <strong>Sentinel</strong>-2A, the <strong>PDGS</strong> will assume different operational roles in time<br />

as driven by the launch of the <strong>Sentinel</strong>-2 units and their respective commissioning phases:<br />

○ Following <strong>Sentinel</strong>-2A Launch and Early Operations Phase (LEOP) and payload switchon<br />

activities, the <strong>PDGS</strong> will start operating its services vis-à-vis the <strong>Sentinel</strong>-2 system<br />

according to the Commissioning Phase requirements. During this phase, the <strong>PDGS</strong><br />

services vis-à-vis downstream entities such as the <strong>GSC</strong>DA will not be considered<br />

operational.<br />

○ Following successful commissioning phase of the <strong>Sentinel</strong>-2A unit (assumed 3 months<br />

after launch), the <strong>PDGS</strong> will start full operations vis-à-vis the <strong>GSC</strong> with one-spacecraft.<br />

○ Following <strong>Sentinel</strong>-2B LEOP and payload switch-on activities, the <strong>PDGS</strong> will, in parallel<br />

to its operational role vis-à-vis <strong>Sentinel</strong>-2A, support the commissioning activities of the<br />

additional unit. During this phase, the <strong>PDGS</strong> services vis-à-vis downstream entities<br />

such as the <strong>GSC</strong>DA are considered operational for <strong>Sentinel</strong>-2A only.<br />

○ Following successful commissioning phase of the <strong>Sentinel</strong>-2B unit, the <strong>PDGS</strong> will reach<br />

its final operational phase vis-à-vis the <strong>Sentinel</strong>-2 constellation.<br />

In this respect, the scope of the document includes the operation concepts applicable to all<br />

four of the above phases. The applicability of the <strong>PDGS</strong> services and operations specific to<br />

Phase-E1 or Phase-E2 of each spacecraft unit will be clarified in the relevant sections.<br />

In particular, a specific interface of the <strong>Sentinel</strong>-2 <strong>PDGS</strong> with CNES (Centre National d’Etudes<br />

Spatiales) in Toulouse will be activated during the commissioning periods of <strong>Sentinel</strong>-2A and<br />

<strong>Sentinel</strong>-2B as required in the <strong>Sentinel</strong>-2 Ground-Segment Requirements Document [GSRD]<br />

[RD-03].<br />

<strong>ESA</strong> UNCLASSIFIED – For Official Use<br />

© <strong>ESA</strong><br />

The copyright of this document is the property of <strong>ESA</strong>. It is supplied in confidence and shall not be reproduced, copied or<br />

communicated to any third party without written permission from <strong>ESA</strong>.