Chapter 16. <strong>Delivery</strong> <strong>Plan</strong> <br />

16.1 The IDP concludes that over the plan period, the amount of forecasted development, in<br />

conjunction with the subsequent growth in population will require new or improved<br />

infrastructure to be provided. The key areas which have been identified are:<br />

• Provision of additional early years, primary and secondary school places will<br />

be required to support growth over the plan period;<br />

• Improvements to the <strong>Borough</strong>’s transport network to improve capacity, ease<br />

congestion and improve safety;<br />

• Continued provision of sufficient Suitable Alternative Natural Greenspace<br />

(SANGS) to mitigate against the impact of new residential development on<br />

the Thames Basin Heath Special Protection Area (TBHSPA) over the plan<br />

period;<br />

• Improvements to the <strong>Borough</strong>’s open spaces; and,<br />

• Provision of infrastructure to support the delivery of the mixed use<br />

development which is forecasted to come forward at the former DERA site.<br />

16.2 Improvements will be delivered by a range of providers and through a variety of<br />

budgets. <strong>Delivery</strong> of certain infrastructure will require partnership working between the<br />

private and public sectors, for example at the former DERA site. Some infrastructure, in<br />

particular, improvements to the transport network, will at times, be funded by developer<br />

contributions.<br />

16.3 What is evident from both County and <strong>Borough</strong> capital budgets is that the capital<br />

finances available at the current time to support infrastructure improvements/provision<br />

are at a low level. Specifically, capital spending at <strong>Borough</strong> level is frozen at the current<br />

time. It is unknown how long capital spending will be frozen for. At County level, the<br />

County has produced a medium term financial plan (MTFP) for <strong>2013</strong>/18. As part of this<br />

plan, the County has set a capital programme for the next 5 years of £683 million (this<br />

figure is as stated in the October 2012 budget monitoring review 56 ). A significant<br />

proportion of this money (originally estimated at £197 million 57 ) will be borrowed. The<br />

remainder of the capital funding will come from government grants, revenue and capital<br />

reserves, third party contributions and capital receipts.<br />

16.4 Capital funding for district council led improvements comes principally from capital<br />

receipts from the sale of land and property in the <strong>Council</strong>’s ownership. However, the<br />

increasing costs faced by the <strong>Council</strong>, in conjunction with the reduced revenue budget<br />

from central government, mean that capital receipts play an important tool in ensuring<br />

income to the revenue budget via the investment income that they attract. <strong>Delivery</strong> of<br />

capital improvements will largely be funded through a combination of developer<br />

contributions, other ad hoc capital sources such as lottery funding and where available,<br />

the use of capital receipts.<br />

16.5 In terms of infrastructure which is expected to be required over the plan period, it is<br />

considered that infrastructure can either be considered as ‘essential’ or ‘desirable’. The<br />

IS in Appendix 1 categorises the forecast infrastructure as such. As noted in chapter 1<br />

of this report, essential infrastructure in this context represents items without which the<br />

development forecasted in the Local <strong>Plan</strong> could not come forward. Desirable<br />

infrastructure represents items which, whilst not vital to unlock growth, will support<br />

growth and benefit local communities over the plan period.<br />

56<br />

Budget monitoring-October 2012<br />

57<br />

Surrey County <strong>Council</strong> Medium Term Financial <strong>Plan</strong> 2012-2017, Section 1: Overview <br />

Page | 167<br />