Figure 11 - <strong>Runnymede</strong>'s Strategic Road Network<br />

6.6 The Highways Agency has however carried out works to improve the M3/M25 junction<br />

within the <strong>Borough</strong> given the levels of congestion experienced. Specifically, a<br />

temporary change was carried out to the road layout in March 2007, designed to try<br />

and reduce the overall delay at junction 12 of the M25. Given the positive results<br />

achieved during the trial period, the revised layout has been permanently changed, with<br />

works being completed in September 2009.<br />

Local <strong>Plan</strong><br />

6.7 Local <strong>Plan</strong> location policies LP01-LP08, confirm the quantity and general location of<br />

new development in the <strong>Borough</strong> over the plan period. These policies conclude that<br />

development would largely be focussed in the <strong>Borough</strong>’s Urban Areas and at the<br />

former DERA site in Longcross. Growth is also envisaged at RHUL. Development in all<br />

of these areas over the plan period is likely to increase the number of residents and<br />

businesses in the <strong>Borough</strong> using the SRN.<br />

6.8 Strategic policy 9 (SP09): Sustainable Transport (which should be read alongside the<br />

location policies) states however, that it will be sought to reduce reliance on the private<br />

Page | 50<br />

<strong>Runnymede</strong> IDP DRAFT – <strong>Feb</strong>ruary <strong>2013</strong>