B. Spillways:<br />
The Spillway arrangement consists <strong>of</strong> one Gated Chute<br />
Spillway on right bank, 2 nos ungated Shaft Spillways on<br />
Right Bank, (Shaft T-3 & T-4), 2 nos. gated Shaft Spillways<br />
on Left Bank (Shaft T-1 & T-2) and an Intermediate Level<br />
Outlet (ILO).<br />
The work <strong>of</strong> Chute Spillway and Stilling Basin has been<br />
completed. A total quantity <strong>of</strong> 8.67 Lac Cum concrete has<br />
been placed in these structures. ILO and T-3 circuit has<br />
been completed and water is flowing through the circuit.<br />
The work fo T-4 circuit is in advance stage <strong>of</strong> completion.<br />
In Shaft T-1,concrete lining from EI. 668.50 to 815.0 M and<br />
in Shaft T-2, concrete lining from EL 677.0 M to EL 815.0<br />
M has been completed till date and balance works <strong>of</strong> Left<br />
Bank Shaft Spillways are under progress.<br />
Concreting <strong>of</strong> 1st stage plug <strong>of</strong> Tunnel T-2 has been<br />
completed and works <strong>of</strong> 2nd stage plug are in progress.<br />
Closure <strong>of</strong> Tunnel-T-2:<br />
With the closure <strong>of</strong> Diversion Tunnel T-2 on 29th Oct-05,<br />
reservoir impoundment has started.<br />
View <strong>of</strong> Tehri Dam from Chute spill way<br />
C. <strong>Power</strong> House Complex:<br />
MINISTRY OF POWER<br />
i. Civil Works<br />
All the civil works <strong>of</strong> <strong>Power</strong> House Complex have been<br />
successfully completed.<br />
The work <strong>of</strong> Maintenance Gate Shaft No. 4 and its transition<br />
with HRT-4 which had become critical due to very complex<br />
geology has been successfully completed by improvised<br />
construction methodology and massive grouting.<br />
The river joining works <strong>of</strong> TRT-1 & TRT-2 which were<br />
taken-up after closure <strong>of</strong> diversion tunnel T-2 are nearing<br />
completion.<br />
ii. Electro-Mechanical Equipment:<br />
The boxing up <strong>of</strong> Unit-IV, III and II has been completed.<br />
Boxing <strong>of</strong> Unit-1 is in advance stage <strong>of</strong> completion.<br />
Erection <strong>of</strong> all 4 Nos Transformers (306 MVA each), 400<br />
KVA Gas Insulated Switchgear and Gas Insulated Busduct<br />
have also been completed. The various auxiliaries system<br />
including Governor Control Systems in the <strong>Power</strong> House<br />
have been completed and pre-commissioning <strong>of</strong> units<br />
is in progress. The <strong>Power</strong> House Control Room with<br />