38<br />
MINISTRY OF POWER<br />
S.No. Name <strong>of</strong> Scheme(I.C. in MW),Agency<br />
1. Anandpur Sahib (4x33.5),PSEB<br />
2. Mukerian, St.I (3x15), PSEB<br />
3. Chibro (4x60), UJVNL<br />
4. Chilla(4x36), UJVNL<br />
5. Bhadra(1x2), KPCL<br />
6. Sharavathy, Ph-A(10x103.5), KPCL<br />
7. Papanasam(4x7), TNEB<br />
8. Mettur Dam(4x10), TNEB<br />
9. Hirakund-I, U 3&4(2x24), OHPC<br />
g) Achievement during the period 1.4.2005 to<br />
31.12.2005<br />
The following 3 schemes having an aggregate installed<br />
capacity <strong>of</strong> 78 MW have been completed during the year<br />
2005-06 till 31.12.2005 at an actual cost <strong>of</strong> Rs. 117.86<br />
Crores against the estimated cost <strong>of</strong> Rs. 156.48 Crores to<br />
accrue a benefit <strong>of</strong> 98 MW.<br />
Sl. No. Name <strong>of</strong> Scheme(I.C. in MW), Agency<br />
1. Bhadra(1x2 MW), KPCL<br />
2. Papanasam(4x7 MW), TNEB<br />
3. Hirakund-I, U-3&4 (2x24 MW), OHPC<br />
h) Programme for the remaining period <strong>of</strong> the year<br />
2005-06 i.e. from 1.1.2006 to 31.3.2006<br />
The following 6 schemes having an aggregated installed<br />
capacity <strong>of</strong> 1638 MW are programmed for completion<br />
during the remaining period <strong>of</strong> the year 2005-06 to accrue<br />
a benefit <strong>of</strong> 50 MW at an estimated cost <strong>of</strong> Rs. 113.11<br />
Crores. Works on these 6 schemes are in advanced stages<br />
<strong>of</strong> completion.<br />
Sl. No. Name <strong>of</strong> Scheme(I.C. in MW), Agency<br />
1. Anandpur Sahib (4x33.5),PSEB<br />
2. Mukerian, St.I (3x15), PSEB<br />
3. Chibro (4x60), UJVNL<br />
4. Chilla(4x36), UJVNL<br />
5. Sharavathy, Ph-A(10x103.5), KPCL<br />
6. Mettur Dam(4x10), TNEB