units each at Ganguwal and Kotla <strong>Power</strong> Houses has<br />

already been completed. Renovation, Modernization and<br />

Upgradation <strong>of</strong> all the six units <strong>of</strong> 60 mega watt to 66 mega<br />

watt <strong>of</strong> Pong <strong>Power</strong> House has already been completed<br />

which has resulted in additional capacity <strong>of</strong> 36 mega watt<br />

increasing the installed capacity from 360 mega watt to<br />

396 mega watt.<br />

BBMB plans to undertake the Renovation, Modernization<br />

and Upgradation works <strong>of</strong> Bhakra Left Bank <strong>Power</strong> House<br />

machines (5x108 mega watt) which have been in operation<br />

for the last about 40 years. All the five units are proposed<br />

to be uprated from 108 mega watt to 126 mega watt<br />

each. The Renovation, Modernization and Upgradation<br />

<strong>of</strong> Bhakra Left Bank <strong>Power</strong> House is expected to provide<br />

additional capacity <strong>of</strong> 90 mega watt to the system and is<br />

expected to generate additional 88 million units annually<br />

due to improved efficiency. This work shall be carried out<br />

in XI plan.<br />

One unit each <strong>of</strong> Ganguwal and Kotla <strong>Power</strong> Houses which<br />

were supplied by M/S Hitachi, Japan, have been planned<br />

for Renovation, Modernization and Upgradation. With the<br />

proposed Renovation, Modernization and Upgradation <strong>of</strong><br />

Dehar <strong>Power</strong> Plant<br />

MINISTRY OF POWER<br />

one machine each at Ganguwal and Kotla <strong>Power</strong> Houses,<br />

the derated capacity <strong>of</strong> the machines shall be uprated<br />

by 4.44 mega watt and will also result in additional<br />

annual generation <strong>of</strong> 36 million units. During renovation,<br />

replacement <strong>of</strong> major components like runner, governor,<br />

stator, unit transformer and other associated equipment<br />

is envisaged. The work on this scheme has already been<br />

undertaken and is expected to be completed in the year<br />

2006-07.<br />

The Renovation, Modernization and Upgradation work<br />

on the old <strong>Power</strong> Houses has given new lease <strong>of</strong> life to<br />

the machines and is a significant step towards meeting<br />

the aspirations <strong>of</strong> the Nation for adding low cost peaking<br />

power to the system through Renovation, Modernization &<br />

Uprating <strong>of</strong> old power houses as per the National Hydro<br />

Policy.<br />

UPKEEP OF DAMS AND HYDEL CHANNELS<br />

The upkeep <strong>of</strong> Dams and Hydel Channels by Bhakra Beas<br />

Management Board has been <strong>of</strong> high standards, which<br />

are considered the benchmarks for other hydro projects<br />

in the region. Monitoring <strong>of</strong> the health and behaviour <strong>of</strong><br />

dams with the help <strong>of</strong> instruments installed in and around<br />