80<br />

MINISTRY OF POWER<br />

the total capacity portfolio shall comprise 48,000<br />

MW on Company’s own Balance Sheet, 6,000 MW<br />

through Joint Ventures, 1,000 MW through Domestic<br />

Subsidiaries and another 1,000 MW through Overseas<br />

Ventures. However, later the company has set for<br />

itself a revised target <strong>of</strong> 66,000 MW plus by 2017. The<br />

plan also envisages NTPC’s presence in coal mining,<br />

washeries, LNG, power distribution and trading<br />

businesses. Further, major thrust has been laid on<br />

Research & Development and integrated Enterprise<br />

Resource Planning. In essence, by 2017 NTPC aims<br />

to have presence in many countries through different<br />

business vehicles and a combined group annual<br />

turnover <strong>of</strong> Rs.1400 billion.<br />

8.1 CAPACITY ADDITION PROGRAMME : Notably, work<br />

on 8,970 MW capacity addition for benefits in X and<br />

NTPC Auraiya<br />

XI Plan is progressing concurrently. During the X Plan<br />

period, 4000 MW has already been commissioned.<br />

Construction work is going on in 8,970 MW capacity,<br />

comprising 3,710 MW due for benefits in X Plan and<br />

5,260 MW due for benefits in XI Plan. During the year<br />

2004-05, two units <strong>of</strong> 500 MW at Talcher-ll Project, one<br />

unit <strong>of</strong> 500 MW at Ramagundam-lll Project and one unit<br />

<strong>of</strong> 500 MW at Rihand-ll Project were commissioned<br />

ahead <strong>of</strong> schedule. Further, another 500 MW unit has<br />

been commissioned at Rihand-ll in September, 2005.<br />

Thus, the total generating capacity <strong>of</strong> the company has<br />

increased from 21,435 MW to 23,935 MW. In addition<br />

to this, NTPC has formed 50:50 equity participation<br />

JVs with SAIL, which consist <strong>of</strong> CPPs at Durgapur,<br />

Rourkela and Bhilai aggregating 314 MW. Thus, the<br />

total installed capacity <strong>of</strong> NTPC is 24,249 MW.