SWBTB (2/10) 041 (a)<br />

• Release 4 – Protocols, Integrated Care pathways, Interactive Charting,<br />

Tray/Instrument Management, Stock Management, Surveillance and Screening,<br />

Document Management screening, Non-Patient Requests and mobile device<br />

integration.<br />

Taking into account the delays with Lorenzo delivery in 2008, our strategy for 2008-2013<br />

identified a need to continue with our current electronic patient record (iCM) as an interim<br />

solution, whilst ensuring a migration path to Lorenzo in 2009-2011.<br />

3. Latest position on Delivery of Lorenzo Regional Care from CSC/NPfIT<br />

The National Programme for IT (NPfIT) continues to remain a high profile and widely<br />

discussed programme. It has been announced recently that NPfIT would find £600m in<br />

savings within the programme as part of the wider drive to improve efficiency in the<br />

Department of Health and NHS.<br />

Following a review of NPfIT nationally, there will be a scaling back in the amount of<br />

functionality and releases to be delivered in Lorenzo Regional Care. Discussions are still<br />

ongoing at a national level to agree the final deliverables and the implications to local <strong>Trust</strong>s<br />

of the functionality they will not receive. The CIO for <strong>West</strong> Midlands has called a meeting on<br />

the 25 th February, where we will be advised of the latest position and possibly the final<br />

agreement.<br />

Timeframes of early 2011, can be achieved to commence implementation of Release 1 and<br />

2 of Lorenzo, but no timeframes have as yet been agreed for Release 3 until the<br />

renegotiation of the contracts have been concluded with CSC.<br />

4. Risks to the <strong>Trust</strong> of delays with Lorenzo Regional Care<br />

The delays in the delivery of Lorenzo will create the following list of risks to the <strong>Trust</strong>, which<br />

we will need to mitigate.<br />

• If Lorenzo Regional Care is scaled back on functionality to a level which will mean we<br />

do not have a joined up integrated record, then there would be risks attached to<br />

taking even the first 2 releases. However, the alternatives, which would need to be<br />

fully explored, could require the <strong>Trust</strong> to invest in a different solution which would be<br />

very difficult in view of the expected future financial climate.<br />

• If the <strong>Trust</strong> decided to move to Lorenzo Releases 1 and 2, it is likely that it could be<br />

an early adopter for Release 3, but restricted functionality as discussed above. To<br />

enable the fully integrated EPR to be achieved, we may have to procure from CSC<br />

the missing functionality we require.<br />

• The new hospital which will open in 2016 is at this time considered to be supported<br />

by a fully electronic patient record. Any further delays in rolling out functionality to<br />

2