<strong>Forthbank</strong> <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

3.2.4 In summary the DP1 work included the following: initial feasibility work on – grid connection,<br />

transportation and access, the development of initial Conceptual Site Models and an economic<br />

appraisal of the design costs, early stage assessments relating to noise, ecology /ornithology<br />

and investigations into the implication of the proposed wind energy development on<br />

communication links.<br />

3.2.5 Where it was concluded that any concerns could reasonably be expected to be overcome<br />

through design development, and that the site was still economically and technically viable, the<br />

site was then progressed to DP2.<br />

<strong>Development</strong> Phase 2 (DP2) September 2009 – May 2010<br />

3.2.6 The objectives of this phase was to fully costs the civil engineering works necessary to<br />

construct the wind turbines, to verify further the economic and technical viability of the site, and<br />

to work with key statutory consultees and others to resolve any outstanding objections, where<br />

possible. Scoping of the EIA was undertaken at this stage in order to verify the key constraints<br />

and initial activities were progressed to establish whether these were capable of resolution e.g.<br />

bird monitoring was started in September 2009. A scoping opinion was issued by<br />

Clackmannanshire Council in March 2010 following submission of a scoping report on 22<br />

December 2009.<br />

3.2.7 DP2 also included the erection of the temporary wind mast in February 2010 following approval<br />

of the application on 21 January 2010. Ecological surveys started in DP1 (July 2009)<br />

continued into DP3, with final bat surveys undertaken in September 2010.<br />

3.2.8 On concluding this stage, it was established that concerns could be overcome through further<br />

design development or via the incorporation of environmental measures into the scheme. The<br />

site was then progressed to DP3.<br />

<strong>Development</strong> Phase 3 (DP3) June 2010 – October 2010<br />

3.2.9 This stage took the site through the remaining technical and environmental investigations<br />

concluding with the submission of the planning application with supporting in<strong>for</strong>mation (this<br />

ES).<br />

3.2.10 Following internal assessment and confirmation that the site would be taken <strong>for</strong>ward <strong>for</strong><br />

development, PfR has engaged in a comprehensive consultation exercise. Details of the<br />

scoping and consultation undertaken <strong>for</strong> the proposed wind energy development are presented<br />

in Section 3.4 below.<br />

3.3 Design Criteria<br />

3.3.1 The design solution <strong>for</strong> a site crosses all development phases and is based on the considered<br />

application of the following technical, economic and environmental criteria across all<br />

development phases as more in<strong>for</strong>mation becomes available:<br />

November 2010 Chapter 3 Page 3<br />