20.05.2014 Views

Forthbank Wind Energy Development - Partnerships for Renewables

Forthbank Wind Energy Development - Partnerships for Renewables

Forthbank Wind Energy Development - Partnerships for Renewables

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Forthbank</strong> <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

4.8 Civil Works<br />

<strong>Wind</strong> Turbine Foundations<br />

4.8.1 Foundation construction design will be finalised at the detailed design engineering stage.<br />

However, a typical foundation design <strong>for</strong> the candidate turbine is shown in Figure 4.6. Prior to<br />

construction, detailed intrusive ground investigations, will be undertaken at each turbine<br />

location and, depending on the in<strong>for</strong>mation derived from these investigations, modifications<br />

could be made to the foundation designs.<br />

4.8.2 The wind turbines are likely to be installed on rein<strong>for</strong>ced concrete foundations, established on<br />

suitable load bearing strata (following excavation) or on deep piled foundations depending on<br />

ground conditions. The proposed type of foundation <strong>for</strong> the three turbines located on the<br />

landfill area will require a rein<strong>for</strong>ced concrete slab, pile cap and deep piled foundations. The<br />

piles will be required to penetrate through the waste mass and the superficial deposits and be<br />

socketed into the underlying rock. The rein<strong>for</strong>ced concrete foundations measure typically up to<br />

20m in diameter and have a depth of approximately 1.5m. A working area around the concrete<br />

foundations will be restored following construction of the foundation and the tower.<br />

4.8.3 It is assumed that the construction of the turbine foundations will require the excavation of<br />

subsoil to a suitable bearing strata and landfill material prior to installation of deep piles and<br />

pile cap of a suitable <strong>for</strong>m that will maintain adequate containment of leachate within the<br />

landfill. Clay is expected to be present beneath the landfill material. Turbine founding in the<br />

north-eastern part of the site will be located (micro-sited) to avoid the two disused adits in the<br />

area.<br />

4.8.4 Excavated material from Turbine 1 (if appropriate) will be reused <strong>for</strong> access track construction.<br />

Construction of Crane Pads<br />

4.8.5 Each wind turbine requires an area of hard standing to be built adjacent to the turbine<br />

foundation. This provides a stable base on which to lay down turbine components ready <strong>for</strong><br />

assembly and erection, and to site the two cranes necessary to lift the tower sections, nacelle<br />

and rotor into place. The crane hard standing will be left in place following construction in<br />

order to allow <strong>for</strong> the use of similar plant should major components need replacing during the<br />

operation of the proposed wind energy development. These could also be utilised during decommissioning<br />

at the end of the proposed wind energy developments life. The total area of<br />

hard standing at each turbine location, including the turbine foundations and the crane pad will<br />

be approximately 1240m 2 (maximum 20m width x 62m length). Approximately a third of this<br />

area will be dressed back with topsoil and landscaped into the surrounding area upon<br />

completion of turbine erection.<br />

4.8.6 A typical crane hard standing is illustrates in Figure 4.7.<br />

November 2010 Chapter 4 Page 7<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> <strong>Development</strong> Co. Ltd 2010 ©

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!