4.9 Construction of the Proposed <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

Principal Site Operations and Indicative Programme<br />

4.9.1 The construction period <strong>for</strong> the wind energy development will last approximately 6 months and<br />

will comprise the following activities:<br />

• upgrading of existing tracks and passing places, inter-linking the turbine locations<br />

and control building;<br />

• upgrading of the existing access junction;<br />

• <strong>for</strong>mation of site compound including hard standing and temporary site office<br />

facilities;<br />

• construction of crane hard standing areas;<br />

• construction of culverts (if required) under roads to facilitate drainage and maintain<br />

existing hydrology;<br />

• construction of turbine foundations;<br />

• construction of site control building;<br />

• construction of met mast foundation;<br />

• excavation of trenches and cable laying adjacent to site roads;<br />

• connection of on-site distribution and signal cables;<br />

• delivery and erection of wind turbines;<br />

• delivery and erection of permanent meteorological mast;<br />

• commissioning of site equipment; and<br />

• site restoration.<br />

4.9.2 Where possible, operations will be carried out concurrently (thus minimising the overall length<br />

of the construction programme) although they will occur predominantly in the order listed. In<br />

addition, development will be phased such that, at different parts of the site, the civil<br />

engineering works will be continuing whilst wind turbines are being erected. The specific<br />

construction programme will consider mitigation measures as identified elsewhere within the<br />

ES e.g. avoiding key months in respect of ornithological issues. Site restoration will be<br />

programmed and carried out to allow restoration of disturbed areas as early as possible and in<br />

a progressive manner.<br />

4.9.3 All construction activities will adhere to pollution control measures which will be detailed in an<br />

Environmental Management Plan drawn up in consultation with SEPA and other relevant<br />

November 2010 Chapter 4 Page 10<br />