<strong>Forthbank</strong> <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

13.8.3 The impact assessment has taken into account the proposed site’s hydrological regime,<br />

highlighting that the principal effects on-site hydrology will occur during construction. With the<br />

implementation of the site specific EMP/PPP and the successful implementation of mitigation<br />

measures the significance of construction effects on the water quality of the River Forth and<br />

Black Devon catchments are considered to be negligible to minor.<br />

13.8.4 The Firth of Forth SSSI, at the mouth of the River Leven is considered to be a sufficient<br />

distance downstream from the site to be unaffected by the proposed wind energy<br />

development.<br />

Flood Risk<br />

13.8.5 The impact assessment has taken into account the site’s hydrological regime, highlighting that<br />

the principal effects on-site hydrology will occur during the construction and operation phases.<br />

The assessment has also determined that the increased landtake as a result of the proposed<br />

wind energy development will have a negligible to minor effect on the site's runoff rates<br />

following the implementation of mitigation measures.<br />

Soils<br />

13.8.6 Much of the soil cover is expected to have been removed by the landfill in the south-eastern<br />

part of the site and the historical development in the north-western part of the site. The<br />

impacts of the proposed wind energy development on the remaining site soils are considered<br />

to be of minor significance.<br />

Geology<br />

13.8.7 The excavation of foundations and, if required, the penetration of deep (piled) foundations may<br />

have an impact on the local geological resource, in particular near surface coal seams and two<br />

adits located in the north-western part of the site. The construction of the proposed turbine<br />

bases will result in permanent alterations to the site geology. The location of the two adits in<br />

the north-western area of the site will be accurately identified prior to construction to ensure<br />

that the turbine foundations do not impact on the adits.<br />

13.8.8 There<strong>for</strong>e, the overall impact is considered to be minor.<br />

Hydrogeology<br />

13.8.9 The site is underlain by bedrock which is moderately permeable, i.e. fractured or potentially<br />

fractured rocks that do not have a high primary permeability. The aquifers at the site vary in<br />

classification from Vulnerability Class 1 (Only vulnerable to conservative pollutants in the longterm<br />

when continuously and widely discarded and leached) to Vulnerability Class 3 (Aquifers<br />

are classed as being vulnerable to some pollutants) in SEPA vulnerability classification<br />

scheme.<br />

13.8.10 Although the quality of the groundwater body beneath the site has been classified by SEPA as<br />

‘poor’ with a high degree of confidence, the hydrogeology was considered to be sensitive due<br />

November 2010 Chapter 13 Page 37<br />