<strong>Forthbank</strong> <strong>Wind</strong> <strong>Energy</strong> <strong>Development</strong><br />

4.8.14 The access tracks will bear directly on to the underlying strata. Should softer ground be<br />

encountered and where the track is on the landfill cap, it may be necessary to strengthen the<br />

road locally. In order to reduce the thickness of the general road construction, and hence<br />

reduce the quantity of imported stone by up to 30%, a geogrid rein<strong>for</strong>cement layer will be<br />

incorporated into the road construction.<br />

4.8.15 Water crossings have been avoided in the site layout as the majority of the access tracks<br />

almost exclusively follow existing tracks.<br />

4.8.16 The need <strong>for</strong> drainage will be established on-site during construction by observation. Where<br />

ground conditions are of a permeable nature, swales will be utilised <strong>for</strong> drainage to allow<br />

natural filtering of surface water into the ground. Where areas are less free draining, land<br />

drains or drainage ditches will be installed where the topography and ground conditions<br />

dictate. Drainage filters will be installed at suitable locations to filter silts out and reduce flow<br />

rates on steeper section of track. If required, cut off drains will be installed at points to redirect<br />

surface water to minimise washout of roads and/or construction areas.<br />

4.8.17 Drainage is discussed further in Chapter 13 (Hydrology, Hydrogeology and Geology).<br />

Site Accommodation and Temporary Works<br />

4.8.18 One temporary construction compound approximately 50m x 50m is proposed. The location is<br />

shown on Figure 1.2. The construction compound will accommodate all the required welfare<br />

facilities. Other temporary fenced compound areas may be established on turbine craneage<br />

areas as appropriate <strong>for</strong> security of plant in remote parts of the site. These will not require any<br />

additional hard standing to that proposed <strong>for</strong> the craneage areas.<br />

4.8.19 Within six months of the proposed wind energy development becoming operational, all<br />

portacabins, machinery and equipment will be removed and the laydown area fully restored.<br />

Stone and Concrete Requirements and Sourcing<br />

4.8.20 Stone and sand materials <strong>for</strong> site tracks, laydown areas, crane hard standings and cable<br />

trenches are expected to be sourced from local quarries. Approximately 10,500t of stone and<br />

7,400t of sand will be required.<br />

4.8.21 Approximately 3,000m 3 of concrete will be imported to site from ready mix plants <strong>for</strong><br />

construction of the turbine foundations and control building.<br />

4.8.22 As noted above, existing on-site tracks will be upgraded and utilised where possible in order to<br />

minimise the amount of stone that is required to be imported to site.<br />

Borrow Pits<br />

4.8.23 No borrow pits are required or proposed on the site.<br />

November 2010 Chapter 4 Page 9<br />